Motion 21-168, authorizing the County Executive to sign Supplement No.18 to Professional Services Agreement CCF07-13 with WSP USA, INC. to provide Consulting Services for the Index Galena Road (MP 6.4-6.9) Flood Repair Project
body
DEPARTMENT: Public Works
ORIGINATOR: Lori White
EXECUTIVE RECOMMENDATION: Approve
PURPOSE: Approval of Supplement No.18 will allow Public Works to continue working with WSP USA, Inc. to provide the necessary Engineer-of-Record Construction Support Services for the Index Galena Road Flood Repair Project.
BACKGROUND:
FISCAL IMPLICATIONS:
EXPEND: FUND, AGY, ORG, ACTY, OBJ, AU
CURRENT YR
2ND YR
1ST 6 YRS
102 50630314109 Capital Program - Consultant
$386,110
$386,110
$1,158,328
TOTAL
$386,110
$386,110
$1,158,328
REVENUE: FUND, AGY, ORG, REV, SOURCE
CURRENT YR
2ND YR
1ST 6 YRS
Road Fund 102
$386,110
$386,110
$1,158,328
TOTAL
$386,110
$386,110
$1,158,328
DEPARTMENT FISCAL IMPACT NOTES: This project is on the adopted 2021-2026 TIP under project No. D.41.02
CONTRACT INFORMATION:
ORIGINAL
CONTRACT
# CCF07-13
AMOUNT
$ 1,137,640.00
AMENDMENT 1
CONTRACT
# CCF07-13
AMOUNT
$ 32,214.00
AMENDMENT 2
CONTRACT
# CCF07-13
AMOUNT
$ 3,506.00
AMENDMENT 3
CONTRACT
# CCF07-13
AMOUNT
$ 0.00
AMENDMENT 4
CONTRACT
# CCF07-13
AMOUNT
$ 0.00
AMENDMENT 5
CONTRACT
# CCF07-13
AMOUNT
$ 24,998.00
AMENDMENT 6
CONTRACT
# CCF07-13
AMOUNT
$ 10,661.00
AMENDMENT 7
CONTRACT
# CCF07-13
AMOUNT
$ 1,376,105.00
AMENDMENT 8
CONTRACT
# CCF07-13
AMOUNT
$ 0.00
AMENDMENT 9
CONTRACT
# CCF07-13
AMOUNT
$ 148,281.00
AMENDMENT 10
CONTRACT
# CCF07-13
AMOUNT
$ 0.00
AMENDMENT 11
CONTRACT
# CCF07-13
AMOUNT
$ 0.00
AMENDMENT 12
CONTRACT
# CCF07-13
AMOUNT
$ 28,621.00
AMENDMENT 13
CONTRACT
# CCF07-13
AMOUNT
$ 0.00
AMENDMENT 14
CONTRACT
# CCF07-13
AMOUNT
$ 0.00