File #: 2024-0320    Version: 1
Type: Motion Status: Approved
File created: 3/12/2024 In control: General Legislative Session
On agenda: 4/10/2024 Final action: 4/10/2024
Title: Motion 24-123, approving and authorizing the County Executive to execute the Right-of-Way Plan for 84th St NE & 123rd Ave NE Intersection Safety Improvements; RC1790; UPI# 22-0013
Attachments: 1. Motion 24-123, 2. Staff Report, 3. Right-of-Way Plan, 4. Funding Estimate, 5. Motion Assignment Slip

 

 

Executive/Council Action Form (ECAF)

 

 

ITEM TITLE:

Title

Motion 24-123, approving and authorizing the County Executive to execute the Right-of-Way Plan for 84th St NE & 123rd Ave NE Intersection Safety Improvements; RC1790; UPI# 22-0013

body

DEPARTMENT:  Public Works

 

ORIGINATOR:  Oscar Fuentes, P.E.

 

EXECUTIVE RECOMMENDATION:  Approved by Ken Klein 3/12/24

 

PURPOSE: Approval of this Right-of-Way (ROW) plan will allow the ROW acquisition phase for the 84th St NE / 123rd Ave NE Intersection Improvements project.

 

BACKGROUND: The County proposes to construct a roundabout at the 84th ST NE / 123rd Ave NE intersection to improve traffic flow and safety.  The project is consistent with the 84th Street NE Safety study completed in December 2019.  Property from eleven (11) parcels is to be acquired for this project. The Right-of-Way acquisition process is scheduled to occur in 2024 and 2025.  The project is located within Council District #1.  Funding has been secured through a $1.68 million Highway Safety Improvement Program (HSIP) federal grant and a $1.45 million Rural Arterial Program (RAP) state grant.  NEPA has been completed for the project.  Community outreach completed to date includes mailers (2,600), project website, one-on-one coordination with 12 out of 12 parcels, and a public meeting (November 2021.)

 

FISCAL IMPLICATIONS:

EXPEND: FUND, AGY, ORG, ACTY, OBJ, AU

CURRENT YR

2ND YR

1ST 6 YRS

102 50630326101 Land Acquisition

$1,184,000

$81,000

$1,265,000

102 50630324109 Appraisals

$84,000

 

$84,000

 

 

 

 

 

 

 

 

TOTAL

$1,268,000

$81,000

$1,349,000

 

 

REVENUE: FUND, AGY, ORG, REV, SOURCE

CURRENT YR

2ND YR

1ST 6 YRS

Road Fund 102

$1,268,000

$81,000

$1,349,000

 

 

 

 

 

 

 

 

 

 

 

 

TOTAL

$1,268,000

$81,000

$1,349,000

 

DEPARTMENT FISCAL IMPACT NOTES:  This project is included in the adopted 2024-2029 Transportation Improvement Plan (TIP) and the adopted 2024 Annual Construction Program (ACP) as Item D.67.02 “84 St NE / 123 Ave NE Intersection Safety Improvements.”

 

CONTRACT INFORMATION:

ORIGINAL

 

CONTRACT#

 

AMOUNT

 

AMENDMENT

 

CONTRACT#

 

AMOUNT

 

 

Contract Period

ORIGINAL

START

 

END

 

AMENDMENT

START

 

END

 

 

OTHER DEPARTMENTAL REVIEW/COMMENTS:  84th St NE / 123rd Ave NE Intersection Safety Improvements - Right-of-Way Plan / RC#1790; UPI#22-0013

 

Reviewed/approved by Finance - Nathan Kennedy 3/12/24