Snohomish Logo
File #: 2022-1212    Version: 1
Type: Motion Status: Approved
File created: 11/17/2022 In control: General Legislative Session
On agenda: 12/14/2022 Final action: 12/14/2022
Title: Motion 22-502, authorizing the County Executive to sign Professional Services Agreement CCF03-22 with TranTech Engineering, LLC to provide design services for the Snohomish River Bridge #1 Scour Mitigation Project
Attachments: 1. Motion 22-502, 2. Staff Report, 3. Agreement - SIGNED, 4. Certificate of Liability Insurance, 5. Motion Assignment Slip

 

 

Executive/Council Action Form (ECAF)

 

 

ITEM TITLE:

Title

Motion 22-502, authorizing the County Executive to sign Professional Services Agreement CCF03-22 with TranTech Engineering, LLC to provide design services for the Snohomish River Bridge #1 Scour Mitigation Project

body

DEPARTMENT:  Public Works

 

ORIGINATOR:  Lori Ericsson (White)

 

EXECUTIVE RECOMMENDATION:  Ken Klein (11/18/22)

 

PURPOSE: Approval of Agreement CCF03-22 will allow Snohomish County Public Works to utilize TranTech Engineering, LLC to provide Design Services necessary to complete the Snohomish River Bridge #1 Scour Mitigation project.

 

BACKGROUND: The Department of Public Works (PW) has received federal bridge program funding to complete a scour mitigation project on Snohomish River Bridge #1 which carries Airport Way/Avenue D over the Snohomish River. The 360-foot-long three span bridge was built in 1983.  This is a heavily used crossing with an average daily traffic count of 16,383, of which 11% are trucks and it is the alternate route for North and South bound SR9 Bridge 9/118.  The bridge scour evaluation, updated in November 2019, showed the bridge scour as ‘critical’ with a National Bridge Inspection Standard/Washington State Bridge Inventory System scour code of 3. The Engineering Services division of PW does not currently have the staff capacity to complete Design Services for this project. Through a Request for Qualifications (RFQ) PW has solicited the services of a consultant to assist the County with this project.  TranTech Engineering, LLC. was one of three consulting firms responding to RFQ-22-005SB and was selected through established Federal, State and County policies and practices. This agreement will include  surveying, geotechnical engineering, environmental permitting, cultural resources, hydrology, constructability reviews, 100% structural design, assistance during bidding and construction related design services. A Professional Services Agreement between Snohomish County and TranTech Engineering, LLC. was negotiated. The total budget for this ECAF is $874,052.30, which includes the agreement amount of $794,593.00 and an additional 10% contingency amount of $79,459.30, for allowable unforeseen costs. The approving motion for the agreement authorizes the Public Works Director or Deputy Director to approve and execute amendments to the agreement within this total budgeted amount.

 

FISCAL IMPLICATIONS:

EXPEND: FUND, AGY, ORG, ACTY, OBJ, AU

CURRENT YR

2ND YR

1ST 6 YRS

102 50630314109 Capital Consultant

$0

$265,000

$794,593

 

 

 

 

 

 

 

 

 

 

 

 

TOTAL

$0

$265,000

$794,593

 

 

REVENUE: FUND, AGY, ORG, REV, SOURCE

CURRENT YR

2ND YR

1ST 6 YRS

Road Fund 102

$0

$72,345

$216,924

102 3064442023 Federal DOT BROS

 

$192,655

$577,669

 

 

 

 

 

 

 

 

TOTAL

$0

$265,000

$794,593

 

DEPARTMENT FISCAL IMPACT NOTES:  This project is in the adopted 2022 - 2027 TIP under project no. F.59.

 

CONTRACT INFORMATION:

ORIGINAL

 

CONTRACT#

CCF03-22

AMOUNT

$794,593.00

AMENDMENT

 

CONTRACT#

 

AMOUNT

 

 

Contract Period

ORIGINAL

START

Execution

END

12/31/2026

AMENDMENT

START

 

END

 

 

OTHER DEPARTMENTAL REVIEW/COMMENTS:  Reviewed/approved by:  Risk Management (Sheila Barker 11/14/22) and Finance (Nathan Kennedy 11/18/22)