Snohomish Logo
File #: 2022-1120    Version: 1
Type: Motion Status: Approved
File created: 10/19/2022 In control: General Legislative Session
On agenda: 11/9/2022 Final action: 11/9/2022
Title: Motion 22-458, authorizing approval of Construction Change Order No. 6 for Meadowdale Beach Park and Estuary Restoration Project
Attachments: 1. Motion 22-458, 2. Change Order 6 - SIGNED, 3. Motion Assignment Slip

 

 

Executive/Council Action Form (ECAF)

 

 

Title

Motion 22-458, authorizing approval of Construction Change Order No. 6 for Meadowdale Beach Park and Estuary Restoration Project

body

DEPARTMENT:  Conservation & Natural Resources

 

ORIGINATOR:  Rachel Dotson

 

EXECUTIVE RECOMMENDATION:  Lacey Harper (10/20/22)

 

PURPOSE: Approve Change Order No. 6

 

BACKGROUND: Change Order No. 6 in the amount of $373,222.60 ($337,758.01 plus 10.5% sales tax) and an additional forty-four (44) calendar days to the contract completion date and incorporates work as described in Change Order Proposal No. 14 which includes work to mitigate impacted soil and groundwater, Change Order Proposal No. 15 which includes work for buried obstructions found within the railroad embankment, Change Order No. 16 which includes additional support needed to assist in BNSF’s installation of 2 bridges, Change order No. 17 which includes painting of the 2 bridges.

 

FISCAL IMPLICATIONS:

EXPEND: FUND, AGY, ORG, ACTY, OBJ, AU

CURRENT YR

2ND YR

1ST 6 YRS

309-51094621346599 - Grant Portion

$281,148.30

 

 

309-51094621366599 - Bond/Other Portion

$31,739.52

 

 

 

 

 

 

 

 

 

 

TOTAL

$373,222.60

 

 

 

 

REVENUE: FUND, AGY, ORG, REV, SOURCE

CURRENT YR

2ND YR

1ST 6 YRS

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

TOTAL

 

 

 

 

DEPARTMENT FISCAL IMPACT NOTES:  Funding available within current budget.

 

CONTRACT INFORMATION:

ORIGINAL

0

CONTRACT#

PW-002-21SB

AMOUNT

$7,519,427.90

AMENDMENT

1

CONTRACT#

PW-002-21SB

AMOUNT

$113,905.87

AMENDMENT

2

CONTRACT#

PW-002-21SB

AMOUNT

$177,442.78

AMENDMENT

3

CONTRACT#

PW-002-21SB

AMOUNT

$53,159.61

AMENDMENT

4

CONTRACT#

PW-002-21SB

AMOUNT

$0.00 (Time Only)

AMENDMENT

5

CONTRACT#

PW-002-21SB

AMOUNT

$283,156.40

AMENDMENT

6

CONTRACT#

PW-002-21SB

AMOUNT

$373,222.60

 

Contract Period

ORIGINAL

START

06/15/2021

END

07/20/2022

AMENDMENT

START

10/19/2022

END

04/03/2023

 

OTHER DEPARTMENTAL REVIEW/COMMENTS:  Reviewed/approved by Risk Management (Sheila Barker 10/21/22) and Finance (Brian Haseleu 10/20/22)