File #: 2022-0769    Version: 1
Type: Motion Status: Approved
File created: 8/5/2022 In control: Administrative Session
On agenda: 8/9/2022 Final action: 8/9/2022
Title: Motion 22-334, authorizing the Executive to approve Change Order No. 12 to Contract CA03-21 with Goodfellow Bros LLC
Attachments: 1. Motion 22-334, 2. Staff Report, 3. Change Order No. 12 - SIGNED, 4. Change Order No. 10 Executed, 5. Change Order No. 9 Executed, 6. Change Order No. 8 Executed, 7. Change Order No. 7 Executed, 8. Change Order No. 6 Executed, 9. Change Order No. 5 Executed, 10. Change Order No. 4 Executed, 11. Change Order No. 3 Executed, 12. Change Order No. 2 Executed, 13. Change Order No. 1 Executed, 14. Original Contract, 15. Motion Assignment Slip, 16. Change Order No. 11 Executed

 

 

Executive/Council Action Form (ECAF)

 

 

ITEM TITLE:

Title

Motion 22-334, authorizing the Executive to approve Change Order No. 12 to Contract CA03-21 with Goodfellow Bros LLC

body

DEPARTMENT:  Public Works

 

ORIGINATOR:  Brian Larmore, P.E.

 

EXECUTIVE RECOMMENDATION:  Approved Ken Klein 08/08/22

 

PURPOSE: To approve Change Order #12 to authorize payment to the Contractor, Goodfellow Bros. for importing additional material due to the shortage of useable material on site.

 

BACKGROUND: • Snohomish County and Goodfellow Bros. entered into agreement #CA03-21 on March 10, 2021 for construction of the Index-Galena Flood Repair project. • The project Contract assumed a large amount of native, on-site material could be used in construction of the new alignment. • Native material on site proved unsuitable to a greater degree than anticipated. • Additional imported gravel borrow embankment material is required to construct the new roadway. • The Index-Galena Flood Repair project is in Council District 5.

 

FISCAL IMPLICATIONS:

EXPEND: FUND, AGY, ORG, ACTY, OBJ, AU

CURRENT YR

2ND YR

1ST 6 YRS

102 50630356399 Contractor Payments

$657,206.00

 

$657,206.00

 

 

 

 

 

 

 

 

 

 

 

 

TOTAL

 

 

 

 

 

REVENUE: FUND, AGY, ORG, REV, SOURCE

CURRENT YR

2ND YR

1ST 6 YRS

Road Fund 102

$657,206.00

 

$657,206.00

 

 

 

 

 

 

 

 

 

 

 

 

TOTAL

 

 

 

 

DEPARTMENT FISCAL IMPACT NOTES:  RC1532, D41.02A in the 2022 ACP

 

CONTRACT INFORMATION:

ORIGINAL

 

CONTRACT#

CA03-21

AMOUNT

$18,105,074.00

AMENDMENT

1

CONTRACT#

CA03-21

AMOUNT

$3,204.98

AMENDMENT

2

CONTRACT#

CA03-21

AMOUNT

$0.00

AMENDMENT

3

CONTRACT#

CA03-21

AMOUNT

$85,000.00

AMENDMENT

4

CONTRACT#

CA03-21

AMOUNT

$-63,410.50

AMENDMENT

5

CONTRACT#

CA03-21

AMOUNT

$70,463.73

AMENDMENT

6

CONTRACT#

CA03-21

AMOUNT

$40,548.23

AMENDMENT

7

CONTRACT#

CA03-21

AMOUNT

$26,250.00

AMENDMENT

8

CONTRACT#

CA03-21

AMOUNT

$105,000.00

AMENDMENT

9

CONTRACT#

CA03-21

AMOUNT

$198,650.00

AMENDMENT

10

CONTRACT#

CA03-21

AMOUNT

$195,000.00

AMENDMENT

11

CONTRACT#

CA03-21

AMOUNT

$485,000.00

 

Contract Period

ORIGINAL

START

03/10/2021

END

At completion

AMENDMENT #1

START

05/21/2021

END

At completion

AMENDMENT #2

START

06/10/2021

END

At completion

AMENDMENT #3

START

08/18/2021

END

At completion

AMENDMENT #4

START

03/24/2022

END

At completion

AMENDMENT #5

START

03/21/2022

END

At completion

AMENDMENT #6

START

12/17/2021

END

At completion

AMENDMENT #7

START

07/12/2022

END

At completion

AMENDMENT #8

START

07/12/2022

END

At completion

AMENDMENT #9

START

07/14/2022

END

At completion

AMENDMENT #10

START

08/01/2022

END

At completion

AMENDMENT #11

START

PENDING

END

At completion

 

OTHER DEPARTMENTAL REVIEW/COMMENTS:  Reviewed/approved by Risk - Diane Baer 08/05/22. Reviewed/approved by Finance - Nathan Kennedy 08/05/22