File #: 2021-0352    Version: 1
Type: Motion Status: Approved
File created: 5/24/2021 In control: General Legislative Session
On agenda: 6/23/2021 Final action: 6/23/2021
Title: Motion 21-199, authorizing the County Executive to execute Change Order No. 6 to the contract for Entry Redesign at Flowing Lake County Park
Attachments: 1. Motion 21-199, 2. Change Order No. 6 Flowing Lake TDICO6 - SIGNED, 3. Motion Assignment Sheet, 4. Staff Report

 

 

Executive/Council Action Form (ECAF)

 

 

ITEM TITLE:

Title

Motion 21-199, authorizing the County Executive to execute Change Order No. 6 to the contract for Entry Redesign at Flowing Lake County Park

body

DEPARTMENT:  Conservation & Natural Resources

 

ORIGINATOR:  Sharon Swan

 

EXECUTIVE RECOMMENDATION:  Approve

 

PURPOSE: Approve Change Order No. 6 to the construction contract for reconstruction of the entrance to Flowing Lake Park.

 

BACKGROUND: Notice to Proceed was issued to Terra Dynamics, Inc. to begin work on reconstruction of the entrance to Flowing Lake Park on Oct. 7, 2019.  Work completed as part of this project includes widening 48th St SE, relocation of a water main running through the park, stormwater system installation, circulation reconfiguration and construction of a new Ranger Office/Welcome Station.  As construction has progressed five Change Orders have been executed and a final Change Order has been negotiated to address a permit requirement to provide fall protection fencing as well as additional geotechnical observations during construction.  The value of this work is $13,954.66 and will be the last Change Order associated with this project.

 

FISCAL IMPLICATIONS:

EXPEND: FUND, AGY, ORG, ACTY, OBJ, AU

CURRENT YR

2ND YR

1ST 6 YRS

309-51094603326599

$13,954.66

 

 

 

 

 

 

 

 

 

 

 

 

 

 

TOTAL

$13,954.66

 

 

 

 

REVENUE: FUND, AGY, ORG, REV, SOURCE

CURRENT YR

2ND YR

1ST 6 YRS

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

TOTAL

 

 

 

 

DEPARTMENT FISCAL IMPACT NOTES:  Funding available within current budget

 

CONTRACT INFORMATION:

ORIGINAL

 

CONTRACT#

055-19SB

AMOUNT

$1,980,000.00

AMENDMENT

1

CONTRACT#

 

AMOUNT

$67,413.01

 

2

 

 

AMOUNT

$46,294.85

 

3

 

 

AMOUNT

$65,405.13

 

4

 

 

AMOUNT

$36,301.69

 

5

 

 

AMOUNT

Time Extension Only

 

6

 

 

AMOUNT

$13,954.66

 

Contract Period

ORIGINAL

START

 

END

 

AMENDMENT

START

 

END

 

 

OTHER DEPARTMENTAL REVIEW/COMMENTS:  Approved/Reviewed by Finance and Risk