Executive/Council Action Form (ECAF)
ITEM TITLE:
Title
Bid Award Recommendation PW-24-027SB for Construction of the New Start Center of Everett to Marpac Construction in the amount of $4,040,000.00, plus applicable Washington State sales tax
body
DEPARTMENT: Facilities Management
ORIGINATOR: Bill Thornton, Purchasing Manager
EXECUTIVE RECOMMENDATION: Ken Klein, Executive Director 11/7/24
PURPOSE: Bid Award Recommendation PW-24-027SB
BACKGROUND: A competitive Bid was issued for the construction of the New Start Center of Everett.
FISCAL IMPLICATIONS:
EXPEND: FUND, AGY, ORG, ACTY, OBJ, AU |
CURRENT YR |
2ND YR |
1ST 6 YRS |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
TOTAL |
|
|
|
REVENUE: FUND, AGY, ORG, REV, SOURCE |
CURRENT YR |
2ND YR |
1ST 6 YRS |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
TOTAL |
|
|
|
DEPARTMENT FISCAL IMPACT NOTES: Click or tap here to enter text.
CONTRACT INFORMATION:
ORIGINAL |
|
CONTRACT# |
|
AMOUNT |
|
AMENDMENT |
|
CONTRACT# |
|
AMOUNT |
|
Contract Period
ORIGINAL |
START |
|
END |
|
AMENDMENT |
START |
|
END |
|
OTHER DEPARTMENTAL REVIEW/COMMENTS: Click or tap here to enter text.