Executive/Council Action Form (ECAF)
ITEM TITLE:
Title
Authorizing the Executive to sign Change Order CO-32 to Bid PW-24-027SB for the Construction at the New Start Center of Everett with Marpac Construction LLC.
body
DEPARTMENT: Facilities and Fleet Management
ORIGINATOR: Lance Meinhold
EXECUTIVE RECOMMENDATION: Approved
PURPOSE: To obtain Executive approval of Change Order 32 to Marpac Construction.
BACKGROUND: The County and Marpac Construction entered into an agreement on December 18th, 2024, for the construction phase of the New Start Center of Everett. The bid allowance for the exterior walkway has been exhausted due to the replacement of the western stairway at Building A and the replacement of the load-bearing columns and beams. The second level columns at Building A were all replaced due to previous weather damage, which could not be assessed until the decorative covers had been removed. The railings were structurally tied to the columns and also had to be removed. The design, engineering, and construction teams accessed several options for the replacement railing. The selected system was the most cost effective. The railing can be replaced while other work is occurring at Building B.
FISCAL IMPLICATIONS:
EXPEND: FUND, AGY, ORG, ACTY, OBJ, AU
CURRENT YR
2ND YR
1ST 6 YRS
002 5123116201
$89,575.00
TOTAL
$89,575.00
REVENUE: FUND, AGY, ORG, REV, SOURCE
CURRENT YR
2ND YR
1ST 6 YRS
TOTAL
DEPARTMENT FISCAL IMPACT NOTES: Click or tap here to enter text.
CONTRACT INFORMATION:
ORIGINAL
CONTRACT #
PW 24-027SB
AMOUNT
$4,040,000.00
AMENDMENT|1010|CONTRACT #
PW 24-027SB
AMOUNT
$12,354.58
AMENDMENT|1010|CONTRACT #
PW 24-027SB
AMOUNT
$71,578.14
AMENDMENT|1010|CONTRACT #
PW 24-027SB
AMOUNT
$7,040.92
AMENDMENT|1010|CONTRACT #
PW 24-027SB
AMOUNT
$16,843.95
AMENDMENT|1010|CONTRACT #
PW 24-027SB
AMOUNT
$200,329.05
AMENDMENT|1010|CONTRACT #
PW 24-027SB
AMOUNT
$143,596.21
AMENDMENT|1010|CONTRACT #
PW 24-027SB
AMOU...