Legislation Details

File #: 2026-0311    Version: 1
Type: Executive Status: Executive Approved
File created: 1/26/2026 In control: Executive
On agenda: Final action: 2/3/2026
Title: Authorizing the Executive to sign Change Order CO-32 to Bid PW-24-027SB for the Construction at the New Start Center of Everett with Marpac Construction LLC.
Attachments: 1. PW-24-027SB Certificate of Insurance, 2. PW24-027SB Tracking Log, 3. PW-24-027SB Agreement, 4. Motion 24-417, Amended, 5. PW-24-027SB Change Order 01, 6. PW-24-027SB Change Order 02, 7. PW-24-027SB Change Order 03, 8. PW-24-027SB Change Order 04, 9. PW-24-027SB Change Order 05, 10. PW-24-027SB Change Order 06, 11. PW-24-027SB Change Order 07, 12. PW-24-027SB Change Order 08, 13. PW-24-027SB Change Order 09, 14. PW-24-027SB Change Order 10, 15. PW-24-027SB Change Order 11, 16. PW-24-027SB Change Order 12, 17. PW-24-027SB Change Order 13, 18. PW-24-027SB Change Order 14, 19. PW-24-027SB Change Order 15, 20. PW-24-027SB Change Order 16, 21. PW-24-027SB Change Order 17, 22. PW-24-027SB Change Order 18, 23. PW-24-027SB Change Order 19, 24. PW-24-027SB Change Order 20, 25. PW-24-027SB Change Order 21, 26. PW-24-027SB Change Order 22, 27. PW-24-027SB Change Order 23, 28. PW-24-027SB Change Order 24, 29. PW-24-027SB Change Order 25, 30. PW-24-027SB Change Order 26, 31. PW-24-027SB Change Order 27, 32. PW-24-027SB Change Order 28, 33. PW-24-027SB Change Order 29, 34. PW-24-027SB Change Order 30, 35. PW-24-027SB Change Order 31, 36. PW-24-027SB Change Order 32 - SIGNED
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.


Executive/Council Action Form (ECAF)


ITEM TITLE:
Title
Authorizing the Executive to sign Change Order CO-32 to Bid PW-24-027SB for the Construction at the New Start Center of Everett with Marpac Construction LLC.
body
DEPARTMENT: Facilities and Fleet Management

ORIGINATOR: Lance Meinhold

EXECUTIVE RECOMMENDATION: Approved

PURPOSE: To obtain Executive approval of Change Order 32 to Marpac Construction.

BACKGROUND: The County and Marpac Construction entered into an agreement on December 18th, 2024, for the construction phase of the New Start Center of Everett. The bid allowance for the exterior walkway has been exhausted due to the replacement of the western stairway at Building A and the replacement of the load-bearing columns and beams. The second level columns at Building A were all replaced due to previous weather damage, which could not be assessed until the decorative covers had been removed. The railings were structurally tied to the columns and also had to be removed. The design, engineering, and construction teams accessed several options for the replacement railing. The selected system was the most cost effective. The railing can be replaced while other work is occurring at Building B.

FISCAL IMPLICATIONS:
EXPEND: FUND, AGY, ORG, ACTY, OBJ, AU
CURRENT YR
2ND YR
1ST 6 YRS
002 5123116201
$89,575.00














TOTAL
$89,575.00




REVENUE: FUND, AGY, ORG, REV, SOURCE
CURRENT YR
2ND YR
1ST 6 YRS
















TOTAL




DEPARTMENT FISCAL IMPACT NOTES: Click or tap here to enter text.

CONTRACT INFORMATION:
ORIGINAL

CONTRACT #
PW 24-027SB
AMOUNT
$4,040,000.00
AMENDMENT|1010|CONTRACT #
PW 24-027SB
AMOUNT
$12,354.58
AMENDMENT|1010|CONTRACT #
PW 24-027SB
AMOUNT
$71,578.14
AMENDMENT|1010|CONTRACT #
PW 24-027SB
AMOUNT
$7,040.92
AMENDMENT|1010|CONTRACT #
PW 24-027SB
AMOUNT
$16,843.95
AMENDMENT|1010|CONTRACT #
PW 24-027SB
AMOUNT
$200,329.05
AMENDMENT|1010|CONTRACT #
PW 24-027SB
AMOUNT
$143,596.21
AMENDMENT|1010|CONTRACT #
PW 24-027SB
AMOU...

Click here for full text