Executive/Council Action Form (ECAF)
ITEM TITLE:
Title
Motion 25-525, authorizing the County Executive to execute Amendment No. 1 to the Interlocal Agreement between Snohomish County and the City of Mill Creek for the Library Park Improvements
body
DEPARTMENT: DCNR/Parks and Recreation
ORIGINATOR: Connie Price
EXECUTIVE RECOMMENDATION: Approved by Mike Fong 11/10/25
PURPOSE: To extend the existing ILA Agreement with the City of Mill Creek for the Library Park Improvements.
BACKGROUND: One of the identified County/City Projects for 2024 is the City of Mill Creek Library Park Improvements. Snohomish County has agreed to provide two hundred fifty thousand ($250,000) of REET II funds in support of the Project. The original ILA was executed on May 15, 2024, and is set to expire on December 31, 2025. The City has asked for more time due to delays working with additional funding for the project from a Dept. of Commerce Grant. Parks and Recreation has reviewed their request and agreed to extend the agreement through 12/31/2026. Expedited processing is requested to ensure the amendment is completed before the end of the year.
FISCAL IMPLICATIONS:
|
EXPEND: FUND, AGY, ORG, ACTY, OBJ, AU |
CURRENT YR |
2ND YR |
1ST 6 YRS |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
TOTAL |
|
|
|
|
REVENUE: FUND, AGY, ORG, REV, SOURCE |
CURRENT YR |
2ND YR |
1ST 6 YRS |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
TOTAL |
|
|
|
DEPARTMENT FISCAL IMPACT NOTES: Click or tap here to enter text.
CONTRACT INFORMATION:
|
ORIGINAL |
X |
CONTRACT# |
ILA |
AMOUNT |
$250,000 |
|
AMENDMENT |
X |
CONTRACT# |
Amendment No. 1 |
AMOUNT |
$0 |
Contract Period
|
ORIGINAL |
START |
May 15, 2024 |
END |
December 31, 2025 |
|
AMENDMENT |
START |
Date of Execution |
END |
December 31, 2026 |
OTHER DEPARTMENTAL REVIEW/COMMENTS: Reviewed/approved by: Risk Management (Diane Baer 11/4/25) and Finance (Nathan Kennedy 11/4/25)