Legislation Details

File #: 2026-2067    Version: 1
Type: Motion Status: Pending Assignment to Committee
File created: 8/10/2026 In control: Planning and Community Development Committee
On agenda: Final action:
Title: Motion 26-323, authorizing the Executive to approve Change Order No. 1 to Contract SW-26-0716LY with John Eager Roofing LLC
Attachments: 1. Proposed Motion 26-323, 2. Change Order, 3. Agreement, 4. Motion Assignment Slip
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Executive/Council Action Form (ECAF)

 

 

ITEM TITLE:

Title

Motion 26-323, authorizing the Executive to approve Change Order No. 1 to Contract SW-26-0716LY with John Eager Roofing LLC

body

DEPARTMENT:  DCNR/Parks/Fair

 

ORIGINATOR:  Connie Price/Thomas Hartzell

 

EXECUTIVE RECOMMENDATION:  Approved by Thomas Teign 8/13/26

 

PURPOSE: Approval of Change Order #1 to authorize payment to the contractor, John Eager Roofing LLC, for added work associated with fascia and roof substrate on the roof of the display hall.

 

BACKGROUND: Snohomish County and John Eager Roofing entered into agreement #SW-26-0716LY on May 6, 2026, for roof repairs at the display hall at the County Fairgrounds. Once the initial work began it was discovered that additional work was needed that was not included in the initial bid. Some fascia and underlaying substrate needed to be replaced. 

 

FISCAL IMPLICATIONS:

EXPEND: FUND, AGY, ORG, ACTY, OBJ, AU

CURRENT YR

2ND YR

1ST 6 YRS

180-509 545 6501

$50,086.52

 

$50,086.52

 

 

 

 

 

 

 

 

 

 

 

 

TOTAL

$50,086.52

 

$50,086.52

 

 

REVENUE: FUND, AGY, ORG, REV, SOURCE

CURRENT YR

2ND YR

1ST 6 YRS

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

TOTAL

 

 

 

 

DEPARTMENT FISCAL IMPACT NOTES:  Sufficient budget authority exists in the approved 2025-2026 budget.

 

CONTRACT INFORMATION:

ORIGINAL

X

CONTRACT#

SW-26-0716LY

AMOUNT

$38,365.30

CO #1

1

CONTRACT#

 

AMOUNT

$11,721.22

 

Contract Period

ORIGINAL

START

05/06/2026

END

COMPLETION

CO #1

START

Upon Execution

END

COMPLETION

 

OTHER DEPARTMENTAL REVIEWCOMMENTS:   Reviewed/approved by Risk Management (Stephanie Rousseau 8/11/26) and Finance (Nathan Kennedy 8/12/26)