Executive/Council Action Form (ECAF)
ITEM TITLE:
Title
Motion 26-147, authorizing approval of Construction Change Order No. 2 for Kayak Point Phase 2 playground surfacing
body
DEPARTMENT: DCNR/Parks and Recreation
ORIGINATOR: Rob Marchand
EXECUTIVE RECOMMENDATION: Approved by Tom Teigen 3/19/26
PURPOSE: Approval of Change Order 2 with OMA Construction Inc. for the Kayak Day Use Phase 2 project.
BACKGROUND: Snohomish County Parks Department went out to bid for Kayak Day Use Phase 2 Bid No. PW-25-0495SB with the playground as a bid alternative to ensure Parks had the funding to support the construction of the new playground. Parks received very competitive bids to install the playground and have funding to support the change from Engineered Wood Fiber to Synthetic turn to provide a more uniform and ADA compliant surfacing. The bid was awarded to OMA Construction Inc. in the amount of $3,605,000.00 (plus applicable sales tax) on December 4, 2025. Change Order 2 is proposed for 369,972.25 (plus applicable sales tax) and is for labor and materials to Replace Engineered Wood Fiber playground surfacing and add 11,614 square feet of Forever Lawn Playground Grass Ultra with 3" safety pad and certified for a 10-foot critical fall height. Includes Envirofill infill, edging in composite board, and seaming tape.
FISCAL IMPLICATIONS:
EXPEND: FUND, AGY, ORG, ACTY, OBJ, AU
CURRENT YR
2ND YR
1ST 6 YRS
309-51094610326599
369,972.25
369,972.25
TOTAL
369,972.25
369,972.25
REVENUE: FUND, AGY, ORG, REV, SOURCE
CURRENT YR
2ND YR
1ST 6 YRS
TOTAL
DEPARTMENT FISCAL IMPACT NOTES: Click or tap here to enter text.
CONTRACT INFORMATION:
ORIGINAL
X
CONTRACT#
AMOUNT
$3,605,000.00
AMENDMENT
X
CONTRACT#
CO #1
AMOUNT
$315,416.44
AMENDMENT
x
CONTRACT#
CO#2
AMOUNT
$369,972.25
Contract Period
ORIGINAL
START
December 4, 2025
END
October 14, 2026
AMENDMENT
START
END
OTHER DEPARTMENTAL REVIEW/COMMENTS: Reviewed/approved by: Risk Manageme...