Executive/Council Action Form (ECAF)
ITEM TITLE:
Title
Motion 24-388, authorizing approval of Construction Change Order No. 4 for Kayak Point Phase 1
body
DEPARTMENT: Conservation and Natural Resources
ORIGINATOR: Rob Marchand
EXECUTIVE RECOMMENDATION: Lacey Harper 9/6/24
PURPOSE: Approve Change Order No. 4
BACKGROUND: Change Order No. 4 is proposed for $267,500.01 (plus applicable sales tax at 7.9%) and incorporates work described in Change Order Proposals (COPs) 5,9,10,16,17,18,19 and summarized: COP 5 special inspections, COP 9 repair trail drainage ditch and culvert, COP 10 over excavation of parking areas, COP 16 southern restroom underground repairs, COP 17 removal and disposal of underground storage tank and hazardous materials, COP 18 landscape and trail drainage issues and extends the contract by 15 days.
FISCAL IMPLICATIONS:
EXPEND: FUND, AGY, ORG, ACTY, OBJ, AU |
CURRENT YR |
2ND YR |
1ST 6 YRS |
309 51094610326599 |
$288,632.51 |
|
$11,606,819 |
|
|
|
|
|
|
|
|
|
|
|
|
TOTAL |
$288,632.51 |
|
$11,606,819 |
REVENUE: FUND, AGY, ORG, REV, SOURCE |
CURRENT YR |
2ND YR |
1ST 6 YRS |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
TOTAL |
|
|
|
DEPARTMENT FISCAL IMPACT NOTES: Click or tap here to enter text.
CONTRACT INFORMATION:
ORIGINAL |
|
CONTRACT# |
PW-23-010SB |
AMOUNT |
$7,595,081.00 |
Change Ord 1 |
|
CONTRACT# |
PW-23-010SB |
AMOUNT |
$107,046.93 |
Change Ord 2 |
|
CONTRACT# |
PW-23-010SB |
AMOUNT |
$253,857.66 |
Change Ord 3 |
|
CONTRACT# |
PW-23-010SB |
AMOUNT |
$3,362,200.90 |
Change Ord 4 |
|
CONTRACT# |
PW-23-010SB |
AMOUNT |
$288,632.51 |
Contract Period
ORIGINAL |
START |
6/15/2021 |
END |
5/15/2024 |
Extension |
START |
6/16/2024 |
END |
6/29/2024 |
Extension |
START |
6/29/2024 |
END |
10/27/2024 |
Extension |
START |
10/28/2024 |
END |
11/11/2024 |
OTHER DEPARTMENTAL REVIEW/COMMENTS: Reviewed/approved by: Risk Management (Sheila Barker 9/4/24) and Finance (Brian Haseleu 9/6/24)