Legislation Details

File #: 2026-1984    Version: 1
Type: Motion Status: Pending Assignment to Committee
File created: 7/31/2026 In control: Planning and Community Development Committee
On agenda: Final action:
Title: Motion 26-305, authorizing the County Executive to sign a Consultant Services Agreement Amendment with Landau Associates Inc. for Paine Field former TECT lease area Agreed Order Implementation at Snohomish County Airport at Paine Field
Attachments: 1. Proposed Motion 26-305, 2. Amendment, 3. Certificate of Insurance, 4. Motion Assignment Slip
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.


Executive/Council Action Form (ECAF)


ITEM TITLE:
Title
Motion 26-305, authorizing the County Executive to sign a Consultant Services Agreement Amendment with Landau Associates Inc. for Paine Field former TECT lease area Agreed Order Implementation at Snohomish County Airport at Paine Field
body
DEPARTMENT: Airport

ORIGINATOR: Andrew Rardin

EXECUTIVE RECOMMENDATION: Approved by Kent Patton 8/4/26

PURPOSE: This is an amendment of a multi-year contract with Landau Associates Inc. to assist in the implementation of the Department of Ecology Agreed Order (AO).

BACKGROUND:

This Agreement is the product of County RFQ No. 23-004BC and Landau Associates Inc. was selected as the most qualified company to perform the services required by the Department of Ecology Agreed Order.

On February 1, 2023, Ecology formally terminated Airport's enrollment in the VCP and deemed the site too complex, and an Agreed Order would be required.

The airport, with assistance of its attorneys, has negotiated an Agreed Order (AO) with the Department of Ecology that requires the County to undertake all actions for remedial work.

The services required by Ecology delineated in the RFQ include, but are not limited to, the following: Task 1: Agreed Order Remedial Investigation/Feasibility Study Work Plan, Task 2: Remedial Investigation Field Work and Report, Task 3: Interim Action(s) (if required), Task 4: Feasibility Study Report(s), Task 5: State Environmental Policy Act (SEPA) Compliance, Task 6: Public Participation, Task 7: Preliminary Draft Cleanup Action Plan. Task 8: Progress Reports.

Snohomish County Council approved a contract with Landau Associates per approved Motion 23-314 to implement the Agreed Order.

The required AO schedule of deliverables have been delayed requiring more time due to multiple site mobilizations to characterize the limits of contamination.

The Airport and Ecology have agreed it is in the best interest of the project to move forward with Interim Ac...