Motion 23-486, approving and authorizing the County Executive to execute the Right-of-Way plan for 18th Ave W sidewalk: 151st St SW to Jefferson Way; RC1789; UPI# 22-0011
body
DEPARTMENT: Public Works
ORIGINATOR: Amber Ortega, E.I.T.
EXECUTIVE RECOMMENDATION: Ken Klein 10/27/23
PURPOSE: Approval of this Right-of-Way (ROW) plan will allow the ROW acquisition phase for the 18th Ave W Sidewalk project.
BACKGROUND: 18th Ave W between 151st St SW & Jefferson Way has no sidewalks on either side and is on the walking path to Oak Heights Elementary. 18th Ave W is listed in the Annual Construction Program (ACP) as item C.00.78. The proposed improvements will add curb, gutter, planter, and sidewalk to create a continuous, accessible pedestrian route. Construction of the project will require right-of-way acquisition from one parcel. Estimates for ROW acquisition are based upon a True Cost Estimate. The project is currently funded through County Road Funds. The project is located in Council District #3.
FISCAL IMPLICATIONS:
EXPEND: FUND, AGY, ORG, ACTY, OBJ, AU |
CURRENT YR |
2ND YR |
1ST 6 YRS |
102 50630326101 Land Acquisition |
|
$141,112 |
$141,112 |
102 50630324109 Appraisal |
|
|
|
|
|
|
|
|
|
|
|
TOTAL |
|
$141,112 |
$141,112 |
REVENUE: FUND, AGY, ORG, REV, SOURCE |
CURRENT YR |
2ND YR |
1ST 6 YRS |
Road Fund 102 |
|
$141,112 |
$141,112 |
|
|
|
|
|
|
|
|
|
|
|
|
TOTAL |
|
$141,112 |
$141,112 |
DEPARTMENT FISCAL IMPACT NOTES: This project is included in the 2023-2028 Transportation Improvement Program (TIP) as Item C.00.78.
CONTRACT INFORMATION:
ORIGINAL |
|
CONTRACT# |
|
AMOUNT |
|
AMENDMENT |
|
CONTRACT# |
|
AMOUNT |
|
Contract Period
ORIGINAL |
START |
|
END |
|
AMENDMENT |
START |
|
END |
|