Executive/Council Action Form (ECAF)
ITEM TITLE:
Title
Motion 23-333, approval of Amendment No 5 to the Agreement for Services with Charles H. Montange for consultation and representation regarding Centennial Trail legal rights
body
DEPARTMENT: DCNR
ORIGINATOR: Rich Patton
EXECUTIVE RECOMMENDATION: Approved by Lacey Harper 8/7/23
PURPOSE: To extend the agreement with outside rail/STB counsel until the end of April 2024 in order to allow time for completion of all Surface Transportation Board and other proceedings and increase the total compensation in order to continue legal efforts (including retaining of paid consultants by outside rail/STB counsel for STB-related work) as previously outlined.
BACKGROUND: An extension of the agreement and additional compensation is needed to cover additional expenses into 2024 to continue to pursue railbanking of the rail corridor. This amendment will allow the retained attorney to advise and represent the County in connection with ongoing litigation associated with thre rail corridor, including in an STB abandonment/railbanking action.
FISCAL IMPLICATIONS:
EXPEND: FUND, AGY, ORG, ACTY, OBJ, AU
CURRENT YR
2ND YR
1ST 6 YRS
309-51094804426599
$135,000
TOTAL
$135,000
REVENUE: FUND, AGY, ORG, REV, SOURCE
CURRENT YR
2ND YR
1ST 6 YRS
TOTAL
DEPARTMENT FISCAL IMPACT NOTES: Click or tap here to enter text.
CONTRACT INFORMATION:
ORIGINAL
CONTRACT#
NA
AMOUNT
$50,000.00
AMENDMENT
1
CONTRACT#
AMOUNT
$35,000.00
AMENDMENT
2
CONTRACT#
AMOUNT
$80,000.00
AMENDMENT
3
CONTRACT#
AMOUNT
$50,000.00
AMENDMENT
4
CONTRACT#
AMOUNT
$50,000.00
AMENDMENT
5
CONTRACT#
AMOUNT
$135,000.00
Contract Period
ORIGINAL
START
02/11/2019
END
12/31/2020
AMENDMENT
START
05/08/2019
END
12/31/2020
AMENDMENT
START
12/04/2019
END
12/31/2020
AMENDMENT
START
12/16/2021
END
12/31/2022
AMENDMENT
START
01/11/2023
END
7/31/2023
AMENDMENT
START
08/0...