Executive/Council Action Form (ECAF)
ITEM TITLE:
Title
Motion 23-306, approving and authorizing the County Executive to execute the Right-of-Way Plan for the Ash Way: 164th St SW to Gibson Rd project; RC1638; UPI# 11-0011
body
DEPARTMENT: Public Works
ORIGINATOR: Oscar Fuentes, P.E.
EXECUTIVE RECOMMENDATION: Approved by Ken Klein 7/14/23
PURPOSE: Approval of this Right-of-Way (ROW) plan will allow the ROW acquisition phase for the Ash Way: 164th St SW to Gibson Rd project.
BACKGROUND: The purpose of the project is to reduce delay, improve safety, promote multi-modal mobility throughout the corridor and provide non-motorized access to future light rail stations. Construction and ROW funding is only secured for Phase 2 (from 135th St SW to Admiralty Way / Gibson Rd). Phase 2 requires ROW acquisition from 59 parcels. Ultimately, the County estimates purchasing ROW from 161 parcels. The ROW stage for Phase 2 is currently funded through County Road Funds and is scheduled to begin in Q3 2023. The project is located within Council District #3. Community outreach completed to date includes mailers (3000 sent), project website, one-on-one coordination with 97 out of 222 parcels, and public meetings (June 2015 and Oct 2022). Public Works and Planning & Development Services have on-going collaboration to review developers' pre-submittals.
FISCAL IMPLICATIONS:
EXPEND: FUND, AGY, ORG, ACTY, OBJ, AU
CURRENT YR
2ND YR
1ST 6 YRS
102 50630326102 Land Acquisitions
$86,000
$1,500,000
$3,086,000
102 50630324101 Appraisals
$413,000
$0
$413,000
TOTAL
$499,000
$1,500,000
$3,499,000
REVENUE: FUND, AGY, ORG, REV, SOURCE
CURRENT YR
2ND YR
1ST 6 YRS
County Road Fund 102
$499,000
$1,500,000
$3,499,000
TOTAL
$499,000
$1,500,000
$3,499,000
DEPARTMENT FISCAL IMPACT NOTES: This project is included in the 2023-2028 Transportation Improvement Plan (TIP) and the adopted 2023 Annual Construction Program (ACP) as Item E.52.01 "Ash Way: 164th St SW to Gibson Rd" ...
Click here for full text