Executive/Council Action Form (ECAF)
ITEM TITLE:
Title
Approving Bid Award Recommendation PW-22-003SB to Allied Plumbing & Pumps LLC dba Allied Trenchless for Cathcart Culvert #1 Rehabilitation, in the amount of $423,300, plus applicable Washington State Sales Tax
body
DEPARTMENT: Public Works
ORIGINATOR: Purchasing, Shannon Barker, Procurement Contracting Officer
EXECUTIVE RECOMMENDATION: Ken Klein, Executive Director
PURPOSE: Bid Award Recommendation PW-22-003SB
BACKGROUND: A formal bid was issued for Cathcart Culvert #1 Rehabilitation. This project includes the rehabilitation of two culverts by the method of resin-impregnated Cured-In-Place Pipe (CIPP). Work shall take place beneath the intersection of two services roads located at the Snohomish County Cathcart Way Operations Center. All work is in accordance with the Contract Plans, Contract Provisions and the 2021 WSDOT Standard Specifications.
FISCAL IMPLICATIONS:
EXPEND: FUND, AGY, ORG, ACTY, OBJ, AU |
CURRENT YR |
2ND YR |
1ST 6 YRS |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
TOTAL |
|
|
|
REVENUE: FUND, AGY, ORG, REV, SOURCE |
CURRENT YR |
2ND YR |
1ST 6 YRS |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
TOTAL |
|
|
|
DEPARTMENT FISCAL IMPACT NOTES: Click or tap here to enter text.
CONTRACT INFORMATION:
ORIGINAL |
|
CONTRACT# |
|
AMOUNT |
|
AMENDMENT |
|
CONTRACT# |
|
AMOUNT |
|
Contract Period
ORIGINAL |
START |
|
END |
|
AMENDMENT |
START |
|
END |
|
OTHER DEPARTMENTAL REVIEW/COMMENTS: Click or tap here to enter text.