Executive/Council Action Form (ECAF)
ITEM TITLE:
Title
Motion 25-416, authorizing Snohomish County to enter into a lease over the east 1.7 acres of land contained on Snohomish County Tax Parcel 31051500101500 for construction staging and storage space for the Arlington Operations Center Renovation Project
body
DEPARTMENT: Facilities and Fleet
ORIGINATOR: Carl Jorgensen
EXECUTIVE RECOMMENDATION: Approved by Ken Klein 9/8/25
PURPOSE: To enter into a lease on property across from the Arlington Operations Center for construction staging and material storage supporting the renovation project of the operations center
BACKGROUND: Snohomish County, through their Public Works Department, is doing a major renovation and build-out project of their current operations center located at 19700 67th Avenue NE, Arlington, WA. To facilitate the renovation project Snohomish County needs additional land to store construction materials and equipment during the life of the project. A vacant lot across the street and directly north of the operations center would be ideal for the purposes previously mentioned. The owner of the vacant lot is willing to lease the County the east 1.7 acres of the vacant lot for $2,035.00 per month.
FISCAL IMPLICATIONS:
EXPEND: FUND, AGY, ORG, ACTY, OBJ, AU
2025
2026
2027-28
ROAOC-400-11-4504
6,105
24,420
48,840
Arlington Ops Center Fund 306, Pgm 501
TOTAL
6,105
24,420
48,840
REVENUE: FUND, AGY, ORG, REV, SOURCE
CURRENT YR
2ND YR
1ST 6 YRS
TOTAL
DEPARTMENT FISCAL IMPACT NOTES: Amount is $2035/mo. (estimated amount is 79,365 through December 2028 per Section 1.(i) of Lease Agreement).
CONTRACT INFORMATION:
ORIGINAL
x
CONTRACT#
AMOUNT
$2,035/mo.
AMENDMENT
CONTRACT#
AMOUNT
Contract Period
ORIGINAL
START
Sept 2025
END
Dec 31, 2028
AMENDMENT
START
END
OTHER DEPARTMENTAL REVIEWCOMMENTS: Risk Management (Diane Baer 9/4/25), Finance (Nathan Kennedy 9/5/25), and Prosecuting Attorney's Office as to form on...