File #: 2024-1117    Version: 1
Type: Motion Status: Approved
File created: 5/23/2024 In control: General Legislative Session
On agenda: 6/26/2024 Final action: 6/26/2024
Title: Motion 24-237, authorizing the Snohomish County Executive to execute Change Order 2 to Contract PW23-004SB with Stacy and Witbeck, Inc. at the Snohomish County Airport
Sponsors: Airport, Nickolis Landgraff
Code sections: SCC 3.04.140 (4) - Amendments, change orders, and orders for extra work for $200,000 or less on contracts subject to bidding requirements for which sufficient appropriation authority exists may be awarded and approved by the county executive, except as provided in subsectio
Attachments: 1. Motion 24-237, 2. Staff Report, 3. Change Order 2 - SIGNED, 4. Change Order 1, 5. Contract, 6. Motion Assignment Slip


Executive/Council Action Form (ECAF)


ITEM TITLE:
Title
Motion 24-237, authorizing the Snohomish County Executive to execute Change Order 2 to Contract PW23-004SB with Stacy and Witbeck, Inc. at the Snohomish County Airport
body
DEPARTMENT: Airport

ORIGINATOR: Kevin Latschaw

EXECUTIVE RECOMMENDATION: A Boungjaktha

PURPOSE: To execute Change Order 2 to the construction contract with Stacy and Witbeck, Inc. to increase the compensation due to the contractor, and extend time for completion.

BACKGROUND: .
* Snohomish County Airport awarded the Terminal Apron Reconstruction (advertisement PW-23-004SB, Motion 23-0288) to Stacy and Witbeck, Inc. (SWI) on 5/5/2023 for $9,344,639.69 inc. applicable sales tax.
* In August 2023, SWI encountered a concrete-encased fiberoptic duct bank running under the terminal apron, at a much shallower depth than had been indicated in record drawings. The duct bank carried most of the airport's fiberoptic network, including the air traffic control tower and portions of the passenger terminal.
* The actual location of the duct bank conflicted with the planned construction and required the removal and reconnection of all associated fiberoptics, in order to reinstall the duct bank at a greater depth.
* Change Order 2, in the amount of $791,181.05 (inc. sales tax) accounts for the cost of relocation, and associated costs due to the delay, as well as adds 34 calendar days to the contract duration.
* The Airport seeks authorization for the Executive to execute this Change Order 2 with SWI in the amount of $791,181.05.
* A prior Change Order 1 was executed on 3/15/2024, for $1,413.16 for various minor quantity adjustments.
* Executing Change Order 2 would bring the new contract total to $10,137,233.90 (inc. sales tax).
* The project is substantially complete as of November 2023, and no additional Change Orders are anticipated to complete the contract.

FISCAL IMPLICATIONS:
EXPEND: FUND, AGY, ORG, ACTY, OBJ, AU
CURRENT YR
2ND YR
1...