Executive/Council Action Form (ECAF)
ITEM TITLE:
Title
Motion 21-178, authorizing the County Executive to sign Amendment No.9 to Professional Services Agreement CC04-17 with Geoengineers, Inc. for the Sisco Landfill Remediation Plan Project
body
DEPARTMENT: Public Works
ORIGINATOR: Lori White
EXECUTIVE RECOMMENDATION: Approve
PURPOSE: Approval of Amendment No. 9 to Professional Services Agreement CC04-17 will allow Snohomish County Public Works to continue using GeoEngineers, Inc. to assist the Department with its Sisco Landfill Remediation Planning efforts.
BACKGROUND:
FISCAL IMPLICATIONS:
EXPEND: FUND, AGY, ORG, ACTY, OBJ, AU
CURRENT YR
2ND YR
1ST 6 YRS
402 50643754101 Professional Services
$48,637
$48,637
TOTAL
$48,637
$48,637
REVENUE: FUND, AGY, ORG, REV, SOURCE
CURRENT YR
2ND YR
1ST 6 YRS
Solid Waste Fund 402
$48,637
$48,637
TOTAL
$48,637
$48,637
DEPARTMENT FISCAL IMPACT NOTES: Funding for this project is included in the 2020 approved budget. Funding for future years will be included in future budgets.
CONTRACT INFORMATION:
ORIGINAL
CONTRACT#
CC04-17
AMOUNT
$ 447,766.00
AMENDMENT 1
CONTRACT#
CC04-17
AMOUNT
$ 40,471.00
AMENDMENT 2
CONTRACT#
CC04-17
AMOUNT
$ 0.00
AMENDMENT 3
CONTRACT#
CC04-17
AMOUNT
$ 271,972.00
AMENDMENT 4
CONTRACT#
CC04-17
AMOUNT
$ 0.00
AMENDMENT 5
CONTRACT#
CC04-17
AMOUNT
$ 3,997.58
AMENDMENT 6
CONTRACT#
CC04-17
AMOUNT
$ 503,197.00
AMENDMENT 7
CONTRACT#
CC04-17
AMOUNT
$ 0.00
AMENDMENT 8
CONTRACT#
CC04-17
AMOUNT
$ 0.00
AMENDMENT 9
CONTRACT#
CC04-17
AMOUNT
$ 48,637.00
Contract Period
ORIGINAL
Start
03/16/2017
End
12/31/2018
AMENDMENT 1
Start
03/18/2018
End
12/31/2018
AMENDMENT 2
Start
12/03/2018
End
12/31/2019
AMENDMENT 3
Start
03/13/2019
End
12/31/2019
AMENDMENT 4
Start
12/02/2019
End
12/31/2020
AMENDMENT 5
Start
06/09/2020
End
12/31/2020
AMENDMENT 6
Start
9/21/2020
End
12/31/2021
AMENDMENT 7
Start
9/24/2020
End
12/31/2021
AMENDME...