Motion 23-317, authorizing the County Executive to authorize a Formal Task Assignment No. 1 to the Public Works On-Call Agreement for Environmental Remedial Investigation Planning and Implementation at Snohomish County Airport at Paine Field
body
DEPARTMENT:  Airport
ORIGINATOR:  Andrew Rardin 
EXECUTIVE RECOMMENDATION:  Approved by A Boungjaktha 7/25/23
PURPOSE: The purpose of this task assignment with GeoEngineers, Inc. is to assist on the Building C-1(Precision/ATS) Site Remedial Investigation Planning & Implementation.
BACKGROUND: .
* The Airport requests authority to utilize the Snohomish County Public Works On-Call Contract for environmental consulting services. 
* GeoEngineers, Inc. ("GeoEngineers") of Seattle was selected to provide environmental consulting services pursuant to the Snohomish County Public Works On-Call Contract Agreement No.  OCC23/2-7.8(U).  
* GeoEngineers previously provided environmental consulting services on the former Precision/ATS lease area.
* Precision vacated the premises and left an undetermined amount contamination that needs further delineation.
* GeoEngineers will assist the Airport on the remedial investigation planning and implementation.
* The value of the formal task assignment no. 1 as part of the On-Call Contract is NTE $263,312.
* Public Works has reviewed the task assignment and has stated that it is contract compliant.
FISCAL IMPLICATIONS: 
EXPEND: FUND, AGY, ORG, ACTY, OBJ, AU
2023
2024
2023-2024
410-521680-4101 - Professional Services
$100,000
$163,312
$263,312
TOTAL
$100,000
$163,312
$263,312
REVENUE: FUND, AGY, ORG, REV, SOURCE
2023
2024
2023-2024
410-321680-0800 - Fund Balance
$100,000
$163,312
$263,312
TOTAL
$100,000
$163,312
$263,312
DEPARTMENT FISCAL IMPACT NOTES:  The Airport Enterprise Fund has sufficient funding in our 2023 budget and has planned accordingly in future years. 