PURPOSE: To authorize approval of Intergovernmental Agreement with Snohomish Conservation District for the Lower Stillaguamish River Basin Pollution Identification and Correction (PIC) Program Phase IV.
BACKGROUND: The County has been awarded a $670,000 Shellfish Pollution Identification and Correction (PIC) Grant for the Lower Stillaguamish River Basin from the Environmental Protection Agency's National Estuary Program. The grant work is designed to reduce fecal coliform impacts to commercial shellfish areas in Port Susan and South Skagit Bay. The Snohomish Conservation District is an ongoing PIC program partner and is identified as subrecipient on the grant to conduct technical assistance and education and outreach work focused on reducing pet and livestock impacts. $171,400 is budgeted for this subrecipient grant work.
FISCAL IMPLICATIONS:
EXPEND: FUND, AGY, ORG, ACTY, OBJ, AU
CURRENT YR
2ND YR
1ST 6 YRS
415 509 5112 5202 (Pass Thru Grants)
$26,000
$59,700
$171,400
TOTAL
$26,000
$59,700
$171,400
REVENUE: FUND, AGY, ORG, REV, SOURCE
CURRENT YR
2ND YR
1ST 6 YRS
415 309 511 6123 (Federal Indirect EPA)
$26,000
$59,700
$171,400
TOTAL
$26,000
$59,700
$171,400
DEPARTMENT FISCAL IMPACT NOTES: Click or tap here to enter text.
CONTRACT INFORMATION:
ORIGINAL
X
CONTRACT#
IGA
AMOUNT
$171,400
AMENDMENT
CONTRACT#
AMOUNT
Contract Period
ORIGINAL
START
Date of Execution
END
9/30/2027
AMENDMENT
START
END