Approving Bid Award Recommendation for Bid PW-23-019SB Jim Creek LWD Restoration to Ecogrind Site Solutions LLC in the amount of $497,050.00 plus applicable Washington State Sales Tax
body
DEPARTMENT: Surface Water Management
ORIGINATOR: Purchasing, Bramby Tollen, Purchasing Manager
EXECUTIVE RECOMMENDATION: Approved by Ken Klein, Executive Director, on 5/11/23
PURPOSE: Bid Award Recommendation Bid PW-23-019SB
BACKGROUND: A competitive Invitation to Bid was issued on behalf of Surface Water Management for improvements to aquatic and riparian habitat at the confluence of Jim and Vos Creeks. The work includes: Installation of 3 Large Deflector ELJs and 5 Small Deflector ELJs within Jim Creek to create hydraulic complexity by redirecting flow, providing high and low velocity zones, and forcing the channel thalweg to meander and create a more sinuous flow path; Targeted excavation to remove the 6-8-inch culvert from Wetland A and to reengage the existing riparian and wetland areas of Jim Creek’s right bank floodplain; Restoration of riparian forest vegetation along Jim Creek and Vos Creek, and other work.
FISCAL IMPLICATIONS:
EXPEND: FUND, AGY, ORG, ACTY, OBJ, AU |
CURRENT YR |
2ND YR |
1ST 6 YRS |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
TOTAL |
|
|
|
REVENUE: FUND, AGY, ORG, REV, SOURCE |
CURRENT YR |
2ND YR |
1ST 6 YRS |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
TOTAL |
|
|
|
DEPARTMENT FISCAL IMPACT NOTES: Click or tap here to enter text.
CONTRACT INFORMATION:
ORIGINAL |
|
CONTRACT# |
|
AMOUNT |
|
AMENDMENT |
|
CONTRACT# |
|
AMOUNT |
|
Contract Period
ORIGINAL |
START |
|
END |
|
AMENDMENT |
START |
|
END |
|
OTHER DEPARTMENTAL REVIEW/COMMENTS: Click or tap here to enter text.