Legislation Details

File #: 2026-1580    Version: 1
Type: Motion Status: Pending Assignment to Committee
File created: 6/18/2026 In control: Public Infrastructure and Conservation Committee
On agenda: Final action:
Title: Motion 26-255, approving and authorizing the County Executive to execute the Right-of-Way Plan for North High Rock Road Slide Repair Project; RC1817; UPI#24-0006
Attachments: 1. Proposed Motion 26-255, 2. Right-of-Way Plan, 3. Estimate, 4. Motion Assignment Slip
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.


Executive/Council Action Form (ECAF)


ITEM TITLE:
Title
Motion 26-255, approving and authorizing the County Executive to execute the Right-of-Way Plan for North High Rock Road Slide Repair Project; RC1817; UPI#24-0006
body
DEPARTMENT: Public Works

ORIGINATOR: Vera Savenkova, P.E.

EXECUTIVE RECOMMENDATION: Approved by Tom Teigen 6/24/26

PURPOSE: Approval of this Right-of-Way (ROW) Plan will allow the ROW acquisition phase for the N High Rock Rd Slide Repair project.

BACKGROUND: ? The N High Rock Rd Slide Repair project is listed as item D.05.15 in the 2026 Annual Construction Program. ? N High Rock Rd provides the sole access route for hundreds of residents south of Monroe. Heavy rains during a December 2023 storm event caused a section of retaining wall and portion of the roadway to fail. The road is currently reduced to a single lane with temporary yield control. ? The County proposes to construct geogrid reinforced walls to restore the two-lane roadway section. ? Property from two (2) parcels is to be acquired for this project. The Right-of-Way acquisition process is scheduled to occur in 2026 and 2027. ? The project is in Council District #1 and ROW funding has been secured through County Road Funds.

FISCAL IMPLICATIONS:
EXPEND: FUND, AGY, ORG, ACTY, OBJ, AU
CURRENT YR
2ND YR
1ST 6 YRS
102 50630326101 (Land Acquisition)
$0
$158,000
$158,000
102 50630324109 (Appraisal)
$14,000
$0
$14,000








TOTAL
$14,000
$158,000
$172,000


REVENUE: FUND, AGY, ORG, REV, SOURCE
CURRENT YR
2ND YR
1ST 6 YRS
Road Fund 102
$14,000
$158,000
$172,000












TOTAL
$14,000
$158,000
$172,000

DEPARTMENT FISCAL IMPACT NOTES: The project is included as item D.05.15 in the adopted 2026 Annual Construction Program (ACP) and the 2026-2031 Six-Year Transportation Improvement Program (TIP).

CONTRACT INFORMATION:
ORIGINAL

CONTRACT#

AMOUNT

AMENDMENT

CONTRACT#

AMOUNT


Contract Period
ORIGINAL
START

END

AMENDMENT
START

END


OTHER DEPARTMENTAL REVIEW/COMMENTS: Re...

Click here for full text