Title: Motion 25-299, authorizing the Snohomish County Executive to execute a Contract Amendment No. 1 to RFQ 23-006BC with Jacobs Engineering Group Inc. at the Snohomish County Airport
Attachments: 1. Proposed Motion 25-299, 2. Agreement, 3. Certificate of Insurance, 4. Motion Assignment Slip

Executive/Council Action Form (ECAF2025-1927)


ITEM TITLE:
Title
Motion 25-299, authorizing the Snohomish County Executive to execute a Contract Amendment No. 1 to RFQ 23-006BC with Jacobs Engineering Group Inc. at the Snohomish County Airport
body
DEPARTMENT: Airport

ORIGINATOR: Kevin Latschaw

EXECUTIVE RECOMMENDATION: Approved by Mike Fong 6/16/25

PURPOSE: To execute Amendment No. 1 to RFQ 23-006BC with Jacobs Engineering Group Inc. for on-call environmental services at Snohomish County Airport.

BACKGROUND:

* Snohomish County Airport (the Airport) and Jacobs Engineering Group Inc. (Jacobs) entered into an on-call contract for Environmental Services in June of 2024.
* Jacobs was selected on the basis of their qualifications to do the work as identified in RFQ 23-006BC.
* The work to be performed under this RFQ was based on a scope of services to provide on-call Environmental analysis in support of the Airport's Runway 16R-34L Rehabilitation project.
* As of April, 2025, the Federal Aviation Administration (FAA) as part of the Runway 16R-34L project has required the Airport to analyze additional environmental impacts to the west side of the airfield not originally budgeted in the on-call contract.
* The proposed Amendment No. 1 extends the duration of the contract to December 31, 2028, as well as increases the budget of the contract to $1,500,000 in support of these additional on-call tasks.

FISCAL IMPLICATIONS:
EXPEND: FUND, AGY, ORG, ACTY, OBJ, AU
2025
2026-2027
TOTAL 3 years
410-521680.6604-FAA Construction in
$500,000
$1,000,000
$1,500,000
Progress











TOTAL
$500,000
$1,000,000
$1,500,000


REVENUE: FUND, AGY, ORG, REV, SOURCE
2025
2026-2027
TOTAL 3 years
410.621850.0800-Fund Balance
$500,000
$1,000,000
$1,500,000












TOTAL
$500,000
$1,000,000
$1,500,000

DEPARTMENT FISCAL IMPACT NOTES: The airport shall only use this contract when funds are available and approved in the budget. In addition, the airport shall use FAA Gran...