Executive/Council Action Form (ECAF)
ITEM TITLE:
Title
Bid Award Recommendation PW-24-0374SB to Reece Construction for 2025 SWM Culvert Replacements in the amount of $1,844,058.00, plus applicable Washington State sales tax
body
DEPARTMENT: Public Works
ORIGINATOR: Bill Thornton, Purchasing Manager
EXECUTIVE RECOMMENDATION: Ken Klein, Executive Director, 4/2/25
PURPOSE: Bid Award Recommendation PW-24-0374SB
BACKGROUND: A competitive bid was issued for the improvements of 2025 SWM Culvert Replacements and other work. The work on the project shall be in accordance with the Standard Specifications for Road, Bridge and Municipal Construction 2025 edition.
FISCAL IMPLICATIONS:
EXPEND: FUND, AGY, ORG, ACTY, OBJ, AU |
CURRENT YR |
2ND YR |
1ST 6 YRS |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
TOTAL |
|
|
|
REVENUE: FUND, AGY, ORG, REV, SOURCE |
CURRENT YR |
2ND YR |
1ST 6 YRS |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
TOTAL |
|
|
|
DEPARTMENT FISCAL IMPACT NOTES: Click or tap here to enter text.
CONTRACT INFORMATION:
ORIGINAL |
|
CONTRACT# |
|
AMOUNT |
|
AMENDMENT |
|
CONTRACT# |
|
AMOUNT |
|
Contract Period
ORIGINAL |
START |
|
END |
|
AMENDMENT |
START |
|
END |
|
OTHER DEPARTMENTAL REVIEW/COMMENTS: Reviewed/approved by Finance - Nathan Kennedy 4/2/25