Bid Award Recommendation for Thomas’ Eddy Hydraulic Reconnection to Rodarte Construction for award amount of $6,926,370.00 plus applicable Washington State Sales Tax
body
DEPARTMENT: DCNR
ORIGINATOR: Bill Thornton, Purchasing Manager
EXECUTIVE RECOMMENDATION: Approved by Tom Teigen 2/18/26
PURPOSE: Bid Award Recommendation PW-25-0595SB - Thomas’ Eddy Hydraulic Reconnection
BACKGROUND: A competitive bid was issued for the Thomas’ Eddy Hydraulic Reconnection with contemplated work including, but not limited to, reestablishment of floodplain connectivity, restoration of the natural stream processes within and adjacent to the project area and improvement to public access. Work is to be completed in accordance with the requirements set forth in the specifications, drawings and contract documents. Eight (8) bid submittals were received, the lowest responsible bidder being to Rodarte Construction with an award amount of $6,926,370. 00 plus applicable Washington State Sales Tax.
FISCAL IMPLICATIONS:
|
EXPEND: FUND, AGY, ORG, ACTY, OBJ, AU |
CURRENT YR |
2ND YR |
1ST 6 YRS |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
TOTAL |
|
|
|
|
REVENUE: FUND, AGY, ORG, REV, SOURCE |
CURRENT YR |
2ND YR |
1ST 6 YRS |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
TOTAL |
|
|
|
DEPARTMENT FISCAL IMPACT NOTES: Click or tap here to enter text.
CONTRACT INFORMATION:
|
ORIGINAL |
|
CONTRACT# |
|
AMOUNT |
|
|
AMENDMENT |
|
CONTRACT# |
|
AMOUNT |
|
Contract Period
|
ORIGINAL |
START |
|
END |
|
|
AMENDMENT |
START |
|
END |
|
OTHER DEPARTMENTAL REVIEW/COMMENTS: Click or tap here to enter text.