Executive/Council Action Form (ECAF)
ITEM TITLE:
Title
Authorizing the County Executive to sign Change Order CO-13 to Bid PW-24-028SB with Lincoln Construction, Inc. for the Construction at the New Start Center of Edmonds.
body
DEPARTMENT: Facilities and Fleet
ORIGINATOR: Lance Meinhold
EXECUTIVE RECOMMENDATION: Approved
PURPOSE: To obtain Executive approval of Change Order 13 to Lincoln Construction, Inc.
BACKGROUND: The County and Lincoln Construction Inc. (LCi) entered into an agreement on December 19th, 2024, for the construction phase of the New Start Center of Edmonds. Many of the interior, resident room doors have significant structural damage that prevents them from locking properly. This Change Order will cause those doors to be repaired or replaced as best economically possible.
FISCAL IMPLICATIONS:
EXPEND: FUND, AGY, ORG, ACTY, OBJ, AU
CURRENT YR
2ND YR
1ST 6 YRS
124 509 044 66 6201
$43,262.00
TOTAL
$43,262.00
REVENUE: FUND, AGY, ORG, REV, SOURCE
CURRENT YR
2ND YR
1ST 6 YRS
TOTAL
DEPARTMENT FISCAL IMPACT NOTES: Click or tap here to enter text.
CONTRACT INFORMATION:
ORIGINAL
CONTRACT#
PW24-028SB
AMOUNT
$2,474,000.00
AMENDMENT|1010|CONTRACT#
PW24-028SB
AMOUNT
$547,000.00
AMENDMENT|1010|CONTRACT#
PW24-028SB
AMOUNT
$128,884.00
AMENDMENT|1010|CONTRACT#
PW24-028SB
AMOUNT
$-46,570.00
AMENDMENT|1010|CONTRACT#
PW24-028SB
AMOUNT
$13,099.00
AMENDMENT|1010|CONTRACT#
PW24-028SB
AMOUNT
$163,150.00
AMENDMENT|1010|CONTRACT#
PW24-028SB
AMOUNT
$32,132.00
AMENDMENT|1010|CONTRACT#
PW24-028SB
AMOUNT
$160,006.00
AMENDMENT|1010|CONTRACT#
PW24-028SB
AMOUNT
$70,783.00
AMENDMENT|10 10|CONTRACT#
PW24-028SB
AMOUNT
$24,452.00
AMENDMENT
10
CONTRACT#
PW24-028SB
AMOUNT
$16,836.00
AMENDMENT
11
CONTRACT#
PW24-028SB
AMOUNT
$5,416.00
AMENDMENT
12
CONTRACT#
PW24-028SB
AMOUNT
$39,090.00
AMENDMENT
13
CONTRACT#
PW24-028SB
AMOUNT
$43,262.00
TOTAL
$3,671,540.00
Contract Period
ORIGINAL
START
12/19/2024
END
Final Project Accept...