File #: 2025-1918    Version: 1
Type: Motion Status: Approved
File created: 6/10/2025 In control: Committee of the Whole
On agenda: Final action: 6/17/2025
Title: Motion 25-286, authorizing the County Executive to sign of Change Order CO-05 to Bid PW-24-027SB for the construction at the New Start Center of Everett with Marpac Construction LLC
Attachments: 1. Proposed Motion 25-286, 2. Staff Report, 3. Agreement, 4. Change Order 01, 5. Change Order 02, 6. Change Order 03, 7. Change Order 04, 8. Change Order 05, 9. Certificate of Insurance, 10. Amended Motion 24-417, 11. Accounting Tracking Log, 12. Motion Assignment Slip

 

 

Executive/Council Action Form (ECAF)

 

 

ITEM TITLE:

Title

Motion 25-286, authorizing the County Executive to sign of Change Order CO-05 to Bid PW-24-027SB for the construction at the New Start Center of Everett with Marpac Construction LLC

body

 

DEPARTMENT:  Facilities and Fleet Management

 

ORIGINATOR:  Lance Meinhold

 

EXECUTIVE RECOMMENDATION:  Approved by Ken Klein (6/12/2025)

 

PURPOSE: To obtain Executive approval of Change Order 05 to Marpac Construction.

 

BACKGROUND: The County and Marpac Construction entered into an agreement on December 18th, 2024, for the construction phase of the New Start Center of Everett. Marpac priced the project based on the ability to reuse the existing conventional fire alarm system. The City of Everett Fire Department Official is requiring the system to be addressable to have low volume horns, and associated upgrades as is the official’s right to require such per the Fire Code. This is a condition that could not have been know at the time of the bid. The Change Order Proposal has been negotiated down from an initial pre-tax cost of $282,332.57. As of the start of this ECAF file in Legistar, Change Order 04 is in process in Legistar.

 

FISCAL IMPLICATIONS:

EXPEND: FUND, AGY, ORG, ACTY, OBJ, AU

CURRENT YR

2ND YR

1ST 6 YRS

124 509 044 66 6201

$200,329.05

 

 

 

 

 

 

 

 

 

 

 

 

 

 

TOTAL

$200,329.05

 

 

 

 

REVENUE: FUND, AGY, ORG, REV, SOURCE

CURRENT YR

2ND YR

1ST 6 YRS

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

TOTAL

 

 

 

 

DEPARTMENT FISCAL IMPACT NOTES:  Click or tap here to enter text.

 

CONTRACT INFORMATION:

ORIGINAL

 

CONTRACT #

PW 24-027SB

AMOUNT

$4,040,000.00

AMENDMENT

1

CONTRACT #

PW 24-027SB

AMOUNT

$12,254.58

AMENDMENT

2

CONTRACT #

PW 24-027SB

AMOUNT

$71,578.14

AMENDMENT

3

CONTRACT #

PW 24-027SB

AMOUNT

$7,040.92

AMENDMENT

4

CONTRACT #

PW 24-027SB

AMOUNT

$16,843.95

AMENDMENT

5

CONTRACT #

PW 24-027SB

AMOUNT

$200,329.05

 

 

 

 

TOTAL

$4,348,046.64

 

Contract Period

ORIGINAL

START

12/18/2024

END

Final Project Acceptance Date

AMENDMENT

START

Upon Execution

END

Same - Unchanged

 

OTHER DEPARTMENTAL REVIEW/COMMENTS:  Reviewed/approved by Risk (Diane Baer 6/11/2025) and Finance (Nathan Kennedy 6/11/2025).