Title: Motion 21-353, authorizing the County Executive to sign Amendment No. 4 to the software license and services agreement between Snohomish County and Cartegraph, Inc
Attachments: 1. Cartegraph Amendment No.1 Executed, 2. Cartegraph Amendment No. 2 Executed, 3. Cartegraph Amendment No.3 Executed, 4. Motion 21-353, 5. Council Staff Report, 6. Cartegraph Certificate of Liability Insurance, 7. Cartegraph Amendment No.4 - SIGNED, 8. Cartegraph Master Agreement Executed, 9. Motion Assignment Slip, 10. Distribution Sheet

 

 

Executive/Council Action Form (ECAF)

 

 

ITEM TITLE:

Title

Motion 21-353, authorizing the County Executive to sign Amendment No. 4 to the software license and services agreement between Snohomish County and Cartegraph, Inc

body

DEPARTMENT:  Public Works

 

ORIGINATOR:  Lori White

 

EXECUTIVE RECOMMENDATION:  Approved - Ken Klein 9/24/21

 

PURPOSE: Approval of Amendment No. 4 to the Software License and Services Agreement between Snohomish County and Cartegraph, Inc.

 

BACKGROUND: On September 25, 2015 Snohomish County executed a Software License and Services Agreement between Snohomish County and Cartegraph, Inc. for an automated asset maintenance management system which was initially released to the Road Maintenance and Solid Waste divisions of Public Works but has now been implemented department wide. Since that time three amendments have been processed.  The first amendment extended the initial term by six months through August 31, 2021.  The second amendment added additional but related scope and budget. The third amendment renewed all five additional one-year terms for an extended agreement through August 31, 2026. The original solicitation (RFP-14-14DW) allows for the expansion of Cartegraph to other County departments and workgroups. At this time the Department of Conservation and Natural Resources has asked to use Cartegraph as their asset maintenance management system. There is no additional cost to add a new department to the Cartegraph solution however, there is a cost associated with Surface Water and Parks specific domains.  Domains are a bundle of Industry Standard Asset types that are installed as a package using pre-defined relationships and integrated system configurations for preventative maintenance plans and asset condition calculations.   The total amount payable under this agreement will not exceed $2,664,137 which includes $318,525 for five years of annual domain costs and an estimated $31,215 in tax for Amendment No. 4.

 

FISCAL IMPLICATIONS:

EXPEND: FUND, AGY, ORG, ACTY, OBJ, AU

CURRENT YR

2ND YR

1ST 6 YRS

415 50651269103

$38,430

 

$38,430

415 50951269103

 

$39,583

$165,584

309-509-490502

$5,490

$5,655

$29,145

002-509-430-4101

$2,196

$2,262

$11,658

002-509-680-4101

$8,784

$9,047

$46,633

002-509-545-4101

$10,980

$11,309

$58,290

 

 

 

 

TOTAL

$65,880

$67,856

$349,740

 

 

REVENUE: FUND, AGY, ORG, REV, SOURCE

CURRENT YR

2ND YR

1ST 6 YRS

415 3065111770

$38,430

 

$38,430

415 3095111770

 

$39,583

$165,584

Within existing Revenue Sources 309

$5,490

$5,655

$29,145

Within existing Revenue Sources 002

$2,196

$2,262

$11,658

Within existing Revenue Sources 002

$8,784

$9,047

$46,633

Within existing Revenue Sources 002

$10,980

$11,309

$58,290

 

 

 

 

TOTAL

$65,880

$67,856

$349,740

 

DEPARTMENT FISCAL IMPACT NOTES:  Funding for the current year is included in the approved 2021 budget.  Funding for future years will be included in future budget proposals.

 

CONTRACT INFORMATION:

Original

 

CONTRACT#

TC13-15

Amount

$ 1,233,992.80

Amendment 1

 

CONTRACT#

TC13-15

Amount

$                 0.00

Amendment 2

 

CONTRACT#

TC13-15

Amount

$       17,300.00

Amendment 3

 

CONTRACT#

TC13-15

Amount

$ 1,063,103.80

Amendment 4

X

CONTRACT#

TC13-15

Amount

$     349,740.00

 

Contract Period

Original

Start

09/25/2015

End

03/31/2021

Amendment 1

Start

06/14/2017

End

08/31/2021

Amendment 2

Start

03/01/2020

End

08/31/2021

Amendment 3

Start

08/26/2021

End

08/31/2026

Amendment 4

Start

Execution

End

08/31/2026

 