File #: 2026-0007    Version: 1
Type: Motion Status: Pending Executive Signature
File created: 12/18/2025 In control: General Legislative Session
On agenda: 1/7/2026 Final action: 1/7/2026
Title: Motion 26-013, authorizing the County Executive to sign amendments to the 2023-2026 On-Call Consultant Services Master Agreements for the Solid Waste Discipline
Attachments: 1. Motion 26-013, 2. Staff Report, 3. Harris Group - Supplement 5 (PENDING EXECUTIVE SIGNATURE), 4. HDR - Supplement 5 (PENDING EXECUTIVE SIGNATURE), 5. Herrera Environmental Consultants - Supplement 6 (PENDING EXECUTIVE SIGNATURE), 6. Parametrix - Supplement 7 (PENDING EXECUTIVE SIGNATURE), 7. SCS Engineers - Supplement 5 (PENDING EXECUTIVE SIGNATURE), 8. Certificate of Insurance - Harris Group, 9. Certificate of Insurance - HDR, 10. Certificate of Insurance - Herrera Environmental Consultants, 11. Certificate of Insurance - Parametrix, 12. Certificate of Insurance - SCS Engineers, 13. Motion Assignment Slip

 

 

Executive/Council Action Form (ECAF)

 

 

ITEM TITLE:

Title

Motion 26-013, authorizing the County Executive to sign amendments to the 2023-2026 On-Call Consultant Services Master Agreements for the Solid Waste Discipline

body

 

DEPARTMENT:  Public Works

 

ORIGINATOR:  Lori Ericsson

 

EXECUTIVE RECOMMENDATION:  Approved by Ken Klein 12/23/2025

 

PURPOSE: Supplements to the 2023-2026 Solid Waste On-Call Consultant Services Program will allow the Department of Public Works (PW) to utilize consultants on an on-call as-needed basis on time critical projects, and for projects where required staffing and/or expertise is not available.

 

BACKGROUND: Approval of the attached Supplements will allow the Public Works Department to continue to use the consultants for various Solid Waste-related services on an on-call basis when appropriate, or in the case of an emergency.   With recent fee increases Solid Waste is hoping to begin design on several important repair and improvement projects including: Cathcart Transfer Station Tipping Floor replacement, ARTS Transfer Station Scalehouse HVAC Improvements,  NCRTS Transfer Station Replacement - Programing and Feasibility Study, Sisco Landfill Closure, and a Fire Protection and Utility Infrastructure Feasibility Study. Solid Waste is requesting an additional $1,500,000 in contracting capacity for a total maximum of $5,100,000.  This increase is necessary to compensate for the additional work throughout the remainder of the current On-Call period which authorizes work through 2027.  

 

FISCAL IMPLICATIONS:

EXPEND: FUND, AGY, ORG, ACTY, OBJ, AU

CURRENT YR

2ND YR

1ST 6 YRS

Various Solid Waste 402

$1,000,000

$500,000

$1,500,000

 

 

 

 

 

 

 

 

 

 

 

 

TOTAL

$1,000,000

$500,000

$1,500,000

 

 

REVENUE: FUND, AGY, ORG, REV, SOURCE

CURRENT YR

2ND YR

1ST 6 YRS

Solid Waste 402

$1,000,000

$500,000

$1,500,000

 

 

 

 

 

 

 

 

 

 

 

 

TOTAL

$1,000,000

$500,000

$1,500,000

 

DEPARTMENT FISCAL IMPACT NOTES:  Funds for On-Call Consultant Services have been appropriated in the 2026 Budget.  Revenues come from a variety of sources, as indicated on the annual construction programs.  Funds for subsequent years will be requested in the specific year’s budget and will only be used if appropriated by Council.

 

CONTRACT INFORMATION:

Original

X

CONTRACT#

See Exhibit A

Amount

$1,150,000.00

Amendment

X

CONTRACT#

See Exhibit A

Amount

$2,245,000.00

Amendment

X

CONTRACT#

See Exhibit A

Amount

$1,500,000.00

 

Contract Period

Original

Start

12/16/2022

End

12/31/2026

Amendment

Start

09/12/2024

End

12/31/2026

Amendment

Start

Execution

End

12/31/2027

 

OTHER DEPARTMENTAL REVIEW/COMMENTS:  Reviewed/approved by Risk Management (Sheila Barker 12/22/2025) and Finance (Nathan Kennedy 12/22/2025).