File #: 2021-0741    Version: 1
Type: Motion Status: Approved
File created: 9/15/2021 In control: General Legislative Session
On agenda: 9/29/2021 Final action: 9/29/2021
Title: Motion 21-335, authorizing approval of Amendment No. 1 to the agreement for professional services with Shannon & Wilson, Inc. for Meadowdale Beach Park and Estuary Restoration Project
Code sections: SCC 3.04.190 - Service contract not subject to bidding requirements.
Attachments: 1. Motion Assignment Slip, 2. Motion 21-335, 3. Amendment No. 1 - SIGNED, 4. Council Staff Report, 5. Motion 21-110, 6. Certificate of Liability Insurance, 7. Distribution Sheet

 

 

Executive/Council Action Form (ECAF)

 

 

ITEM TITLE:

Title

Motion 21-335, authorizing approval of Amendment No. 1 to the agreement for professional services with Shannon & Wilson, Inc. for Meadowdale Beach Park and Estuary Restoration Project

body

DEPARTMENT:  DCNR - Parks, Recreation & Tourism

 

ORIGINATOR:  Logan Daniels

 

EXECUTIVE RECOMMENDATION:  Approved-Lacey Harper, 09/16/21

 

PURPOSE: To execute Amendment No. 1 to the Professional Services Agreement with Shannon & Wilson, Inc. providing geotechnical related construction management services for the Meadowdale Beach Park and Estuary Restoration Project.

 

BACKGROUND: Shannon & Wilson, Inc., was selected through the County’s Request for Qualifications process (RFQ 002-21SB) to provide  geotechnical related construction management services for the Meadowdale Beach Park and Estuary Restoration Project including:   Construction observation of the geotechnical aspects of the railroad bridge installation activities performed by both BNSF and the County-procured construction contractor;  Construction observation of the geotechnical aspects of the park and habitat elements constructed by the County-procured contractor, including but not limited to access road reinforcement, pedestrian bridge abutments, landslide hazard wall, boardwalk and restroom enclosure foundations, estuary excavation and debris removal;  Monitoring haul route pavement conditions to satisfy neighborhood concerns associated with the large number of truck trips along 75th Place West;  Coordination with the County Construction Manager (CM), BNSF as authorized by the County CM, and other specialty construction management consultants procured under separate RFQ’s, including Railroad and Park/Habitat; Providing environmental remediation consulting services as warranted; and Construction management administrative activities including review of contractor submittals, responding to Requests for Information (RFI’s), and providing geotechnical engineering support as needed.  A Professional Services Agreement in the amount of $399,437 for the above services was signed by the County Executive on April 15, 2021 as authorized by County Council (Motion No. 21-110).  Amendment No. 1 in the amount of $98,480 includes additional construction observation and geotechnical engineering related services associated with the access road stabilization and City of Edmonds right of way use permit, and BNSF pile driving;   The engineer’s estimate for construction by the County-procured contractor, BNSF and consultant services for this project is $15,000,000. Funding for Meadowdale Beach Park and Beach Restoration Project has been included in the Snohomish County Capital Improvement Program CIP since 2016. Funding for the Meadowdale Beach Park and Estuary Restoration Project includes awards from six (6) grants totaling $6,704,078, with the remaining $8,295,922 from REET 2 funding and tax-exempt bond funds as approved in Motion 20-401.  In effort to not impede construction progress and to accommodate budget process this request is marked urgent.

 

FISCAL IMPLICATIONS:

EXPEND: FUND, AGY, ORG, ACTY, OBJ, AU

CURRENT YR

2ND YR

1ST 6 YRS

309-51094621366599 Bond- Constr Svcs (currently within budget)

$ 52,660.90

 

 

309-51094621346599 (FRA Grant)

$ 45,819.10

 

 

 

 

 

 

 

 

 

 

TOTAL

$ 98,480.00

 

 

 

 

REVENUE: FUND, AGY, ORG, REV, SOURCE

CURRENT YR

2ND YR

1ST 6 YRS

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

TOTAL

 

 

 

 

DEPARTMENT FISCAL IMPACT NOTES:  Click or tap here to enter text.

 

CONTRACT INFORMATION:

ORIGINAL

X

CONTRACT#

 

AMOUNT

$ 399,437

AMENDMENT

1

CONTRACT#

 

AMOUNT

$   98,480

 

Contract Period

ORIGINAL

START

4/15/21

END

4/15/23

AMENDMENT

START

Execution

END

4/15/23

 

OTHER DEPARTMENTAL REVIEW/COMMENTS:  PA reviewed and Approved as to Form/Risk Approved S. Barker 09/16/21-Finance-Brian Haseleu-09/16/21