Snohomish Logo
File #: 2023-0693    Version: 1
Type: Motion Status: Approved
File created: 6/13/2023 In control: General Legislative Session
On agenda: 8/23/2023 Final action: 8/23/2023
Title: Motion 23-312, authorizing the County Executive to sign an Agreed Order with the Washington State Department of Ecology for the Former Tect Lease Area on Paine Field Airport
Sponsors: Airport, Nickolis Landgraff
Code sections: Charter 2.20(7) - To approve contracts or establish by ordinance methods by which any type of contract shall be approved
Attachments: 1. Motion 23-312, 2. Staff Report, 3. Contract - SIGNED, 4. Fiscal Worksheet, 5. Motion Assignment Slip

 

 

Executive/Council Action Form (ECAF)

 

 

ITEM TITLE:

Title

Motion 23-312, authorizing the County Executive to sign an Agreed Order with the Washington State Department of Ecology for the Former Tect Lease Area on Paine Field Airport

body

DEPARTMENT:  Airport                     

 

ORIGINATOR:  Andrew Rardin

 

EXECUTIVE RECOMMENDATION:  Approved by A Boungjaktha 7/21/23

 

PURPOSE: Agreed Order Contract between Department of Ecology and Snohomish County for remedial action at Airport.

 

BACKGROUND: .

                     Snohomish County Airport has been investigating environmental contamination at the Former Tect Lease Area since the early 1990’s with Remedial Investigation (RI) reports submitted to the Department of Ecology.

                     On December 13, 2018, Ecology sent the Airport an Early Notice Letter which stated that cleanup would need to occur on the property pursuant to the Model Toxics Control Act (MTCA).

                     On November 23, 2021, the Airport submitted a request to enter the Department of Ecology Voluntary Cleanup Program (VCP).  The VCP program provides oversight of straight forward typical cleanup actions.

                     On March 17, 2022, Ecology provided written notice that the Airport was a Potentially Liable Party (PLP) for the environmental contamination at the former Tect lease area.

                     On February 1, 2023, Ecology formally terminated Airport’s enrollment in the VCP and deemed the site too complex and an Agreed Order (AO) would be required.

                     The Airport, with assistance of its attorneys, has negotiated an Agreed Order with the Department of Ecology that requires the County to undertake all actions for remedial work.

                     The Airport is responsible to reimburse Ecology staff hours worked on the AO which is estimated to be approximately $150,000 per year until completion.

 

FISCAL IMPLICATIONS:

EXPEND: FUND, AGY, ORG, ACTY, OBJ, AU

2023

2024

1ST 3 YRS

API49-20-6301 - Other Improvements

$150,000

$150,000

$450,000

 

 

 

 

 

 

 

 

 

 

 

 

TOTAL

$150,000

$150,000

$450,000

 

 

REVENUE: FUND, AGY, ORG, REV, SOURCE

2023

2024

1ST 3 YRS

410-3216800800 - Fund Balance

$150,000

$150,000

$450,000

 

 

 

 

 

 

 

 

 

 

 

 

TOTAL

$150,000

$150,000

$450,000

 

DEPARTMENT FISCAL IMPACT NOTES:  The Airport Enterprise Fund has sufficient funds for this project and shall budget accordingly in future years.

 

CONTRACT INFORMATION:

ORIGINAL

X

CONTRACT#

AO

AMOUNT

$150,000 Per Year Estimate

AMENDMENT

 

CONTRACT#

 

AMOUNT

 

 

Contract Period

ORIGINAL

START

Upon Execution

END

Until Completion

AMENDMENT

START

 

END

 

 

OTHER DEPARTMENTAL REVIEW/COMMENTS:  Reviewed/approved by Risk - Shelia Barker 7/21/23 and Finance - Nathan Kennedy 7/21/23