Snohomish Logo
File #: 2021-0544    Version: 1
Type: Motion Status: Approved
File created: 7/21/2021 In control: General Legislative Session
On agenda: 8/25/2021 Final action: 8/25/2021
Title: Motion 21-262, approving and authorizing the County Executive to execute the Right-of-Way Plan for 84th St NE & 163rd Ave NE Intersection Improvements; RC1758; UPI# 20-0005
Attachments: 1. Motion 21-262, 2. Council Staff Report, 3. 84th/163rd ROW EXHIBIT, 4. 84th St NE &163 Ave NE IntxImp RC1758 ROW Plan ROW Plan, 5. 84th St NE &163 Ave NE IntxImp RC1758 ROW Plan Funding Estimate, 6. Motion Assignment Sheet, 7. Distribution Sheet

 

 

Executive/Council Action Form (ECAF)

 

 

ITEM TITLE:

Title

Motion 21-262, approving and authorizing the County Executive to execute the Right-of-Way Plan for 84th St NE & 163rd Ave NE Intersection Improvements; RC1758; UPI# 20-0005

body

DEPARTMENT:  Public Works

 

ORIGINATOR:  Michael Randall, P.E.

 

EXECUTIVE RECOMMENDATION:  Approve

 

PURPOSE: Approval of this Right-of-Way (ROW) plan will allow for the ROW acquisition phase for the 84th St NE & 163rd Ave NE Intersection Improvements project

 

BACKGROUND: The 84th St NE / 163rd Ave NE Intersection Improvements project is listed as item D.67.01 in the 2021 Annual Construction Program   The County proposes to construct a roundabout at this intersection to improve traffic flow and safety. The project is consistent with the 84th Street NE Safety study completed in December 2019.   Property from eight (8) parcels is to be acquired for this project.  The Right-of-Way acquisition process is scheduled to occur in 2021 and 2022.  The project is located in Council District #1.   Funding has been secured through a $1.8 million Highway Safety Improvement Program (HSIP) grant.    SEPA and NEPA have been completed for the project.     Community outreach has occurred for the project environmental reviews.

 

FISCAL IMPLICATIONS:

EXPEND: FUND, AGY, ORG, ACTY, OBJ, AU

CURRENT YR

2ND YR

1ST 6 YRS

102-50630326101 (Land Acquisition)

$50,000

$809,000

$859,000

102-50630324109 (Appraisal)

$52,000

$5,000

$57,000

 

 

 

 

 

 

 

 

TOTAL

$102,000

$814,000

$916,000

 

 

REVENUE: FUND, AGY, ORG, REV, SOURCE

CURRENT YR

2ND YR

1ST 6 YRS

102 3064442027 FHWA HSIP Grant

$90,000

$330,000

$420,000

County Road Funds

$12,000

$484,000

$496,000

 

 

 

 

 

 

 

 

TOTAL

$102,000

$814,000

$916,000

 

DEPARTMENT FISCAL IMPACT NOTES:  This project is included in the adopted 2021 Annual Construction Program (ACP) and the adopted 2021-2026 Transportation Improvement Plan (TIP) as Item D.67.01.

 

CONTRACT INFORMATION:

ORIGINAL

 

CONTRACT#

 

AMOUNT

 

AMENDMENT

 

CONTRACT#

 

AMOUNT

 

 

Contract Period

ORIGINAL

START

 

END

 

AMENDMENT

START

 

END

 

 

OTHER DEPARTMENTAL REVIEW/COMMENTS:  Approved/Reviewed by Finance & Risk