File #: 2026-0769    Version: 1
Type: Motion Status: Pending Assignment to Committee
File created: 3/17/2026 In control: Public Infrastructure and Conservation Committee
On agenda: Final action:
Title: Motion 26-143, authorizing the County Executive to sign Change Order CO-02 to Bid PW-24-0427SB for the construction of the Denney Juvenile Justice Center roof repairs - 2025 with V&R Roofing
Attachments: 1. Proposed Motion 26-143, 2. Change Order 2, 3. Change Order 1, 4. Agreement, 5. Worksheet, 6. Certificate of Insurance, 7. Motion Assignment Slip
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

 

 

Executive/Council Action Form (ECAF)

 

 

ITEM TITLE:

Title

Motion 26-143, authorizing the County Executive to sign Change Order CO-02 to Bid PW-24-0427SB for the construction of the Denney Juvenile Justice Center roof repairs - 2025 with V&R Roofing

body

DEPARTMENT:  Facilities and Fleet

 

ORIGINATOR:  Lance Meinhold

 

EXECUTIVE RECOMMENDATION:  Approved by Tom Teigen 3/18/26

 

PURPOSE: To obtain Executive approval of Change Order 02 to V&R Roofing.

 

BACKGROUND: The County and V&R Roofing entered into an agreement on September 25th, 2025, for the Denney Juvenile Justice Center Roof Repairs. A portion of the roofing at the upper level contains a steeper that typical cricket. The thermal imaging scans did not indicate the insulation to be soaked through every layer in the area. However, as wet insulation was removed it was discovered the entire depth of the cricket had been saturated and is required to be removed to maintain the roofing warranty. Additional moisture was also found at the lower roof area. This change order provides for the removal and installation of these areas. The bid documents were supplied by Facilities to Purchasing in February 2025. The Bid was advertised on May 30, 2025. The bids were due on July 1, 2025. The general understanding at the time was the contract would be executed by the end of July and the work would be able to start in August, well before bad weather. This would have allowed the roofers to work with minimal interruptions due to weather related issues. Unfortunately, the contract was not executed until September 25, 2025. Thus, roofers then had to schedule the project around rain forecasts. As a result, the project has been extended an additional four months causing additional costs for rental equipment.

 

FISCAL IMPLICATIONS:

EXPEND: FUND, AGY, ORG, ACTY, OBJ, AU

CURRENT YR

2ND YR

1ST 6 YRS

311 522180016000

$72,696.39

 

 

 

 

 

 

 

 

 

 

 

 

 

 

TOTAL

$72,696.39

 

 

 

 

REVENUE: FUND, AGY, ORG, REV, SOURCE

CURRENT YR

2ND YR

1ST 6 YRS

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

TOTAL

 

 

 

 

DEPARTMENT FISCAL IMPACT NOTES:  Click or tap here to enter text.

 

CONTRACT INFORMATION:

ORIGINAL

 

CONTRACT#

PW-24-0427SB

AMOUNT

$412,733.00

AMENDMENT

1

CONTRACT#

PW-24-0427SB

AMOUNT

$65,214.53

AMENDMENT

2

CONTRACT#

PW-24-0427SB

AMOUNT

$72,696.39

TOTAL

 

 

 

 

$550,643.92

 

Contract Period

ORIGINAL

START

9/25/2025

END

Final Project Acceptance Date

AMENDMENT 1

START

Upon Execution

END

Extended by 15 Days

AMENDMENT 2

START

Upon Execution

END

Extended by 4.5 Months

 

OTHER DEPARTMENTAL REVIEW/COMMENTS:  Reviewed/approved by:  Risk Management (Sheila Barker 3/18/26) and Finance (Nathan Kennedy 3/18/26)