Snohomish Logo
File #: 2023-0825    Version: 1
Type: Motion Status: Approved
File created: 7/7/2023 In control: Administrative Session
On agenda: 11/7/2023 Final action: 11/7/2023
Title: Motion 23-490, approving and authorizing the execution of the agreement between Snohomish County and Ziply Fiber Northwest, LLC
Attachments: 1. Motion 23-490, 2. Agreement - SIGNED, 3. Staff Report, 4. Certificate of Insurance, 5. Motion Assignment Slip

 

 

Executive/Council Action Form (ECAF)

 

 

ITEM TITLE:

Title

Motion 23-490, approving and authorizing the execution of the agreement between Snohomish County and Ziply Fiber Northwest, LLC

body

DEPARTMENT:  Information Technology                     

 

ORIGINATOR:  Dee White                     

 

EXECUTIVE RECOMMENDATION:  Ken Klein 11/1/23

 

PURPOSE: To execute an Agreement with Ziply Fiber Northwest, LLC for the Snohomish County and Ziply State Route 530 Broadband Project.

 

BACKGROUND: The County has received a grant award from the Washington State Department of Commerce, Broadband Office (“WSBO”) to expand broadband services into rural areas of Snohomish County.  The County submitted a joint application for the award with Ziply Fiber NW, LLC a broadband system provider to construct a Fiber to the Premise (FttP) network along or near the State Route 530 Corridor from the City of Arlington to the Town of Darrington. The communities to be connected include Bryant, Trafton, Cicero, Oso, Rowan, Hazel, Swede Heaven, Whitehorse, and Darrington. The proposed project will enable gigabit fiber connectivity to approximately 4,510 addresses. The approved project spans multiple years, includes several complex, industry-specific agreements and is funded through more than $16M in federal recovery grant funding and over $9M in matching funds provided by Ziply Fiber NW. The County has negotiated multiple endpoints and up to 12 strands of fiber in segments throughout the network.  Certain endpoints and segments are adjacent to but outside of the scope of the grant project area and carry an IRU fee to the County of $125,100.  The IT Department is requesting Council approval the contract with Ziply Fiber Northwest, LLC for $25,848,569. This is a multi-year project with funding expiration set for 2025, and is related to ECAF 2023-823. Expedited handling is requested to execute the contract and begin the project immediately.

 

FISCAL IMPLICATIONS:

EXPEND: FUND, AGY, ORG, ACTY, OBJ, AU

2023-2025

 

 

315-51144936401 - Capital

$16,713,615

 

 

130-57516505786401 - Capital

$125,100

 

 

Matching Grant Funds: Ziply Fiber

$9,009,854

 

 

 

 

 

 

TOTAL

$25,848,569

 

 

 

 

REVENUE: FUND, AGY, ORG, REV, SOURCE

CURRENT YR

2ND YR

1ST 6 YRS

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

TOTAL

 

 

 

 

DEPARTMENT FISCAL IMPACT NOTES:  This award was anticipated and included in the IT Fund 315 approved 2023 budget as a multi-year large capital infrastructure project.

 

CONTRACT INFORMATION:

ORIGINAL

X

CONTRACT#

 

AMOUNT

$25,848,569.00

AMENDMENT

 

CONTRACT#

 

AMOUNT

 

 

Contract Period

ORIGINAL

START

7/1/2021

END

6/30/2025

AMENDMENT

START

 

END

 

 

OTHER DEPARTMENTAL REVIEW/COMMENTS:  Reviewed/approved by:  Risk Management (Sheila Barker 10/31/23) and Finance (Nathan Kennedy 10/31/23). Prosecuting Attorney approval 10/27/2023 subject to memorandum