Legislation Details

File #: 2024-0890    Version: 1
Type: Executive Status: Executive Approved
File created: 5/3/2024 In control: Executive
On agenda: Final action: 5/6/2024
Title: Authorizing the County Executive to sign Change Order Number CO-11S to Bid PW23-007SB with Western Ventures Construction for the Paine Field, Tenant Improvements
Attachments: 1. Western Ventures_COI_081524, 2. Motion 23-200, 3. Construction Contract Budget Tracking, 4. PW23-007SB-Change Order 10S_Signed, 5. CO-01S to 07S - All Documents, 6. PW23-007SB-Change Order 08S_Signed, 7. PW23-007SB-Change Order 09S_Signed, 8. PW23-007SB-Change Order 10S_Signed, 9. Motion 24-058 Change Order-05S w Exec Sig Auth, 10. PW23-007SB-Change Order 11S, 11. PW23-007SB-Change Order 11S EXEC SIGNED
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

 

 

Executive/Council Action Form (ECAF)

 

 

ITEM TITLE:

Title

Authorizing the County Executive to sign Change Order Number CO-11S to Bid PW23-007SB with Western Ventures Construction for the Paine Field, Tenant Improvements

body

DEPARTMENT:  Facilities and Fleet

 

ORIGINATOR:  Anna Morton

 

EXECUTIVE RECOMMENDATION:  Approve

 

PURPOSE: To obtain Executive approval of PW-23-007SB Change Order 011S

 

BACKGROUND: The County and Western Ventures Construction Inc. entered into an agreement on June 22, 2023, for the Sheriff’s Office Tenant Improvements, West Precinct Airport project. The West Precinct Sheriff and Paine Field, has a single contract, two funding sources, and three areas of work. The competitive bid and initial contract award for PW-23-007SB covered two areas of the work. The interior improvements for the Sheriff and the Airport. The contract also identified the split of the contract amounts for those work areas to the separate funding sources. The third area of work is the site improvements, which were recently approved as a part of CO-05S.  Change Orders CO-11S covers items typically associated with changes in construction projects. The changes include items for unexpected hidden conditions (furring out of plumbing wall, door type revision, etc.), building inspector requests (ADA accessible holding cell, hot water loop, etc.) and clarifications of design elements that became apparent to the end users after some construction was in place (convenience outlet at the generator, elevator finish upgrades, etc.).  Additionally, the Change Order covers an Owner caused delay in the work in accordance with RCW 4.24.360. The General Contractor has been delayed in proceeding with some of the work due to the length of time used by the design and engineering team to respond to RFIs, issue ASIs, and approve of Change Order Requests. The design and engineering team are working directly for the County and have not been hired by the contractor.

 

FISCAL IMPLICATIONS:

EXPEND: FUND, AGY, ORG, ACTY, OBJ, AU

CURRENT YR

2ND YR

1ST 6 YRS

FMPR-2007-1 6000

$135,105.95 +tax

 

 

311.528180016000

 

 

 

 

 

 

 

 

 

 

 

TOTAL

$135,105.95 +tax

 

 

 

 

REVENUE: FUND, AGY, ORG, REV, SOURCE

CURRENT YR

2ND YR

1ST 6 YRS

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

TOTAL

 

 

 

 

DEPARTMENT FISCAL IMPACT NOTES:  There is sufficient budget authority-no increase requested.

 

CONTRACT INFORMATION:

ORIGINAL

 

CONTRACT#

PW23-007SB

AMOUNT

$3,777,375

CHANGE ORD

01S

CONTRACT#

See Attached

AMOUNT

$87,464.35

CHANGE ORD

02S

CONTRACT#

See Attached

AMOUNT

$249,191.67

CHANGE ORD

03S

CONTRACT#

See Attached

AMOUNT

$117,743.03

CHANGE ORD

04S

CONTRACT#

See Attached

AMOUNT

$9,019.32

CHANGE ORD

05S

CONTRACT#

See Attached

AMOUNT

$665,058.00

CHANGE ORD

06S 

CONTRACT#

See Attached

AMOUNT

$74,074.92

CHANGE ORD

07S 

CONTRACT#

See Attached

AMOUNT

$72,046.13

CHANGE ORD

08S

CONTRACT#

See Attached

AMOUNT

$64,913.65

CHANGE ORD

09S 

CONTRACT#

See Attached

AMOUNT

$10,017.15

CHANGE ORD

10S

CONTRACT#

See Attached

AMOUNT

$99,536.15

CHANGE ORD

11S

CONTRACT#

See Attached

AMOUNT

$135,105.95

                                                                                                                                                                                                TOTAL      $5,361,545.32

 

Contract Period

ORIGINAL

START

6/22/23

END

Final Project Acceptance Date

AMENDMENT

START

Date of Execution

END

No Change

 

OTHER DEPARTMENTAL REVIEW/COMMENTS:  Click or tap here to enter text.