Title: Motion 22-182, authorizing the County Executive to sign Amendment No. 1 to the Intergovernmental Service Agreement with PUD No. 1 of Snohomish County - Customer Service Contract #100076090
Attachments: 1. Motion 22-182, 2. Staff Report, 3. Amendment 1 - EXECUTED COPY, 4. Customer Service Contract Executed, 5. Motion Assignment Slip

 

 

Executive/Council Action Form (ECAF)

 

 

ITEM TITLE:

Title

Motion 22-182, authorizing the County Executive to sign Amendment No. 1 to the Intergovernmental Service Agreement with PUD No. 1 of Snohomish County - Customer Service Contract #100076090

body

 

DEPARTMENT:  Public Works

                     

ORIGINATOR:  Lori White

 

EXECUTIVE RECOMMENDATION:  Approve - Ken Klein

 

PURPOSE: Approval of Amendment No. 1 to Customer Service Contract #100076090 with Snohomish County PUD for engineering services, easement acquisition guidance, permitting, material and construction of utility poles for the 84th St NE / 163rd Ave NE Intersection Improvements project.

 

BACKGROUND: The 84th St NE / 163rd Ave NE Intersection Improvements project is listed as item D.67.01 in the 2022 Annual Construction Program.  The County proposes the construction of a roundabout with shared use sidewalks, shoulders, and drainage facilities to improve traffic flow and safety.  Public Utility District No. 1 (PUD) is the supplier of electrical service at 84th St NE and 163rd Ave NE near Granite Falls.   The original PUD Customer Service Contract was signed by the Executive on 3/1/2021, and identified as PUD Work Order 100076090, authorized PUD to provide engineering services for relocation of four (4) poles outside of the County right-of way and within PUD held utility easements.   As the project progressed additional easement acquisition guidance, permitting, material and construction services were need from PUD for the original four poles plus (3) three additional 12kV distribution poles. The original services were valued at $20,000. PUD estimates the cost of the additional services to be $355,000 for a total not to exceed amount of $375,000. Approval and signature of the attached Customer Service Contract and payment of the estimated $355,000 is required in advance of PUD services.  Any unused funds will be returned to the County.

 

FISCAL IMPLICATIONS:

EXPEND: FUND, AGY, ORG, ACTY, OBJ, AU

CURRENT YR

2ND YR

1ST 6 YRS

102 50630314101 Professional Services

$355,000

 

$355,000

 

 

 

 

 

 

 

 

 

 

 

 

TOTAL

$355,000

 

$355,000

 

 

REVENUE: FUND, AGY, ORG, REV, SOURCE

CURRENT YR

2ND YR

1ST 6 YRS

Road Fund 102

$355,000

 

$355,000

 

 

 

 

 

 

 

 

 

 

 

 

TOTAL

$355,000

 

$355,000

 

DEPARTMENT FISCAL IMPACT NOTES:  Funds are included in the approved 2022 Budget. This project is partially funded through an HSIP (Highway Safety Improvement Program) Grant. This project is listed as item D.67.01 in the 2022 ACP.

 

CONTRACT INFORMATION:

ORIGINAL

 

CONTRACT#

N/A

AMOUNT

$20,000.00

AMENDMENT

X

CONTRACT#

N/A

AMOUNT

$355,000.00

 

Contract Period

ORIGINAL

START

03/24/2021

END

At Completion

AMENDMENT

START

Execution

END

At Completion

 

OTHER DEPARTMENTAL REVIEW/COMMENTS:  Reviewed/approved by Risk and Finance