Title: Amended Motion 25-048, approving and authorizing the County Council Chair to sign the Bid Award Recommendation PW24-0301 for the Swamp Creek Bridge #503 Replacement Project
Attachments: 1. Amended Motion 25-048, 2. Staff Report, 3. Bid Award Recommendation - SIGNED, 4. Memorandum, 5. Bid Tabulation Details, 6. Motion Assignment Slip, 7. Amendment Sheet 1, 8. Proposed Motion 25-048 (REDLINED)

 

 

Executive/Council Action Form (ECAF)

 

 

ITEM TITLE:

Title

Amended Motion 25-048, approving and authorizing the County Council Chair to sign the Bid Award Recommendation PW24-0301 for the Swamp Creek Bridge #503 Replacement Project

body

 

DEPARTMENT:  Public Works

 

ORIGINATOR:  Lori Ericsson

 

EXECUTIVE RECOMMENDATION:  Ken Klein 1/8/25

 

PURPOSE: Approval of Bid Award Recommendation PW24-0301 Swamp Creek Bridge #503 Replacement

 

BACKGROUND: The Department of Public Works (PW) has received federal funding to complete a bridge replacement project on Swamp Creek Bridge #503. Swamp Creek Bridge #503 carries Locust Way across Swamp Creek east of Brier.  The project will replace the existing two span concrete tub girder bridge with a longer and wider single span 70 foot long prestressed concrete wide flange decked girder superstructure with cast-in-place deck supported by drilled shafts and concrete abutment shaft caps. The new bridge will provide facilities for all users including bicycles and pedestrians.   Under Bid PW24-0301, Johansen Construction Company. was determined to be the lowest responsive and responsible bidder. The lowest responsive bid was $3,958,000.00 which is 26.84% higher than the engineers estimate of $3,120,352.50. Under SCC 3.04.165 special approval is required from Council where the bid exceeds the Engineers Estimate by more than 10%. Public Works staff have prepared a memo with their recommendations and justifications for accepting a bid that is more than 10% above the engineers estimate including approval from FHWA to 100% fund the fed-aid portion of the work with the increased bid amount. Approval of the Bid Award Recommendation is sought in order to continue the Swamp Creek Bridge #503 Replacement project.

 

FISCAL IMPLICATIONS:

EXPEND: FUND, AGY, ORG, ACTY, OBJ, AU

CURRENT YR

2ND YR

1ST 6 YRS

102 50630356399 Contractor Payments

$3,958,000.00

 

$3,958,000.00

 

 

 

 

 

 

 

 

 

 

 

 

TOTAL

$3,958,000.00

 

$3,958,000.00

 

 

REVENUE: FUND, AGY, ORG, REV, SOURCE

CURRENT YR

2ND YR

1ST 6 YRS

102 3064442023 Federal DOT

$3,958,000.00

 

$3,958,000.00

 

 

 

 

 

 

 

 

 

 

 

 

TOTAL

$3,958,000.00

 

$3,958,000.00

 

DEPARTMENT FISCAL IMPACT NOTES:  This project is included in the adopted 2025 - 2030 TIP under project F.54

 

CONTRACT INFORMATION:

ORIGINAL

x

CONTRACT#

 

AMOUNT

$3,958,000.00

AMENDMENT

 

CONTRACT#

 

AMOUNT

 

 

Contract Period

ORIGINAL

START

Execution

END

Completion

AMENDMENT

START

 

END

 

 

OTHER DEPARTMENTAL REVIEW/COMMENTS:  Finance (Nathan Kennedy 1/8/25)