Snohomish Logo
File #: 2025-0998    Version: 1
Type: Motion Status: Consent Agenda
File created: 3/18/2025 In control: General Legislative Session
On agenda: 4/23/2025 Final action:
Title: Motion 25-179, authorizing the Snohomish County Executive to execute a contract for RFQ 23-005BC Part B with Jacobs Engineering Group Inc. at the Snohomish County Airport
Code sections: SCC 3.04.140 (11) - Except as provided by ordinance, all contracts shall be awarded and approved by the county council.
Attachments: 1. Proposed Motion 25-179, 2. Staff Report, 3. Agreement, 4. Certificate of Insurance, 5. Motion Assignment Slip

Executive/Council Action Form (ECAF 2025-0998)

 

 

ITEM TITLE:

Title

Motion 25-179, authorizing the Snohomish County Executive to execute a contract for RFQ 23-005BC Part B with Jacobs Engineering Group Inc. at the Snohomish County Airport

body

DEPARTMENT:  Airport

 

ORIGINATOR:  Kevin Latschaw

 

EXECUTIVE RECOMMENDATION:  Mike Fong 3/21/25

 

PURPOSE: To hire Jacobs Engineering Group Inc. for engineering services during construction at Snohomish County Airport on the Taxilane Echo Phase 2 project.

 

BACKGROUND:

                     Snohomish County Airport requires Airfield Engineering Consulting Services in order to accomplish the Taxilane Echo (Phase 2) reconstruction project.

                     Jacobs Engineering Group Inc. (Jacobs) has been selected on the basis of their qualifications to do the work as identified in RFQ 23-005BC.  Jacobs has been in business since 1947 and consults on engineering projects worldwide with over 24,000 employees in the Unites States and 60,000 worldwide.

                     The work to be performed under this RFQ is split into two professional services contracts with Jacobs. The first contract (Part A, executed 8/23/23) consisted of design and bidding services. This contract is the second (Part B) contract and will be for construction engineering services.

                     The Airport seeks authorization for the Executive to execute the Part B professional services contract with Jacobs, for engineering services during construction.

                     The contract is NTE $849,773 and terminates December 31, 2027, with up to two (2) additional two (2) year extensions at the option of the County.

 

 

FISCAL IMPLICATIONS:

EXPEND: FUND, AGY, ORG, ACTY, OBJ, AU

2025

2026-2027

Total

410.521680.6604-FAA Construction in Progress

$749,773

$100,000

$849,773

 

 

 

 

 

 

 

 

 

 

 

 

TOTAL

$749,773

$100,000

$849,773

 

 

REVENUE: FUND, AGY, ORG, REV, SOURCE

2025

2026-2027

Total

 

$749,773

$100,000

$849,773

 

 

 

 

 

 

 

 

 

 

 

 

TOTAL

$749,773

$100,000

$849,773

 

DEPARTMENT FISCAL IMPACT NOTES: 

The airport shall only use this contract when funds are available and approved in the budget.  In addition, the airport shall use FAA Grants or Passenger Facility Charges (PFC) whenever feasible.

 

 

 

 

CONTRACT INFORMATION:

ORIGINAL

X

CONTRACT#

RFQ 23-055BC Part B

AMOUNT

NTE $849,773

AMENDMENT

 

CONTRACT#

 

AMOUNT

 

 

Contract Period

ORIGINAL         X

START

Date of Execution

END

12/31/2027

AMENDMENT

START

 

END

 

 

OTHER DEPARTMENTAL REVIEW/COMMENTS:  Reviewed/approved by:  Risk Management (Sheila Barker 3/21/25), Finance (Nathan Kennedy 3/21/25), and Prosecuting Attorney’s Office as to form only (Michelle Corsi 3/14/25)