Title: Motion 24-206, authorizing the County Executive to sign Change Order Number CO-08 to Bid PW-23-013SB with Bayley Construction, LP for the Third Floor Elections Ballot Facility Remodel
Attachments: 1. Motion 24-206, 2. Staff Report, 3. Change Order 8 - SIGNED, 4. Change Order 7, 5. Change Order 6, 6. Change Order 5, 7. Change Order 4, 8. Change Order 3, 9. Change Order 2, 10. Change Order 1, 11. Change Order Tracking, 12. Addendums 1-5, 13. Agreement, 14. Certificate of Insurance, 15. Motion 23-248, 16. Invitation to Bid, 17. Bid Proposal, 18. Bid Award Letter, 19. Specifications Table of Contents, 20. Drawing Cover Sheet, 21. Motion Assignment Slip

 

 

Executive/Council Action Form (ECAF)

 

 

ITEM TITLE:

Title

Motion 24-206, authorizing the County Executive to sign Change Order Number CO-08 to Bid PW-23-013SB with Bayley Construction, LP for the Third Floor Elections Ballot Facility Remodel

body

DEPARTMENT:  Facilities and Fleet

 

ORIGINATOR:  Anna Morton

 

EXECUTIVE RECOMMENDATION:  Ken Klein 5/3/24

 

PURPOSE: To obtain Council approval of PW-23-013SB Change Order 08

 

BACKGROUND: The County and Bayley Construction, LP entered into an agreement on July 28, 2023, for the Elections Balloting Facility Remodel on the third floor of Admin West. This Change Order covers an Owner caused delay in the work pursuant with RCW 4.24.360. The asbestos abatement work, as separate contract by the owner not the general contractor, was delayed in starting due to difficulty in both the contract negotiations and the ability to find skilled abatement workers capable of passing the County’s background checks. Thus, the start of the general contractor’s scope of work was delayed by four months. The General Contractor has requested additional compensation to cover the costs directly incurred due to this delay in accordance with the RCW. Per SCC 3.04.140(4), this change order increases the contract above the Executive’s authority and now requires Council approval by motion.

 

FISCAL IMPLICATIONS:

EXPEND: FUND, AGY, ORG, ACTY, OBJ, AU

CURRENT YR

2ND YR

1ST 6 YRS

FMPR-1002-2 6000

$144,260.00 + tax

 

 

311.530180016000

 

 

 

 

 

 

 

 

 

 

 

TOTAL

$144,260.00 + tax

 

 

 

 

REVENUE: FUND, AGY, ORG, REV, SOURCE

CURRENT YR

2ND YR

1ST 6 YRS

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

TOTAL

 

 

 

 

DEPARTMENT FISCAL IMPACT NOTES:  There is sufficient budget authority-no increase requested.

 

CONTRACT INFORMATION:

ORIGINAL

 

CONTRACT#

PW-23-013SB

AMOUNT

$2,660,000.00

CHANGE ORD

01

CONTRACT#

See attached

AMOUNT

$152,033.00

CHANGE ORD

02

CONTRACT#

 

AMOUNT

$74,386.00

CHANGE ORD

03

CONTRACT#

 

AMOUNT

$29,078.00

CHANGE ORD

04

CONTRACT#

 

AMOUNT

$44,142.75

CHANGE ORD

05

CONTRACT#

 

AMOUNT

$32,029.00

CHANGE ORD

06

CONTRACT#

 

AMOUNT

$10,088.00

CHANGE ORD

07

CONTRACT#

 

AMOUNT

$66,081.00

CHANGE ORD

08

CONTRACT#

 

AMOUNT

$144,260.00

                                                                                                                                                                        TOTAL                                   $3,212,097.75

 

Contract Period

ORIGINAL

START

7/28/2023

END

Final Project Acceptance Date

AMENDMENT

START

Date of Execution

END

No Change

 

OTHER DEPARTMENTAL REVIEW/COMMENTS:  Reviewed/approved by:  Risk Management (Sheila Barker 5/2/24) and Finance (Nathan Kennedy 5/3/24)