Legislation Details
|
File #:
|
2025-3539
Version:
1
|
|
|
|
Type:
|
Executive
|
Status:
|
Executive Approved
|
|
File created:
|
11/5/2025
|
In control:
|
Executive
|
|
Title:
|
Authorizing the Executive to sign of Change Order CO-25 to Bid PW-24-027SB for the Construction at the New Start Center of Everett with Marpac Construction LLC.
|
|
Attachments:
|
1. PW-24-027SB Certificate of Insurance, 2. PW-24-027SB Agreement, 3. PW24-027SB Tracking Log, 4. Motion 24-417, Amended, 5. PW-24-027SB Change Order 01, 6. PW-24-027SB Change Order 02, 7. PW-24-027SB Change Order 03, 8. PW-24-027SB Change Order 04, 9. PW-24-027SB Change Order 05, 10. PW-24-027SB Change Order 06, 11. PW-24-027SB Change Order 07, 12. PW-24-027SB Change Order 08, 13. PW-24-027SB Change Order 09, 14. PW-24-027SB Change Order 10, 15. PW-24-027SB Change Order 11, 16. PW-24-027SB Change Order 12, 17. PW-24-027SB Change Order 13, 18. PW-24-027SB Change Order 14, 19. PW-24-027SB Change Order 15, 20. PW-24-027SB Change Order 16, 21. PW-24-027SB Change Order 17, 22. PW-24-027SB Change Order 18, 23. PW-24-027SB Change Order 19, 24. PW-24-027SB Change Order 20, 25. PW-24-027SB Change Order 21, 26. PW-24-027SB Change Order 22, 27. PW-24-027SB Change Order 23, 28. PW-24-027SB Change Order 24, 29. PW-24-027SB Change Order 25 - Proposed, 30. PW-24-027SB Change Order 25 - Exec Signed
|
Executive/Council Action Form (ECAF)
ITEM TITLE:
Title
Authorizing the Executive to sign of Change Order CO-25 to Bid PW-24-027SB for the Construction at the New Start Center of Everett with Marpac Construction LLC.
body
DEPARTMENT: Facilities and Fleet Management
ORIGINATOR: Lance Meinhold
EXECUTIVE RECOMMENDATION: Approved
PURPOSE: To obtain Executive approval of Change Order 25 to Marpac Construction.
BACKGROUND: The County and Marpac Construction entered into an agreement on December 18th, 2024, for the construction phase of the New Start Center of Everett. The Salvation Army requested additional CCTV and WAP locations to ensure proper coverage for security purposes. The wall behind the former food prep areas in the kitchen were discovered to be covered in oil and grime when the cabinets were removed. Replacement of the drywall was deemed safer and more simple than attempting to clean the areas.
FISCAL IMPLICATIONS:
|
EXPEND: FUND, AGY, ORG, ACTY, OBJ, AU |
CURRENT YR |
2ND YR |
1ST 6 YRS |
|
002 5123116201 |
$37,182.00 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
TOTAL |
$37,182.00 |
|
|
|
REVENUE: FUND, AGY, ORG, REV, SOURCE |
CURRENT YR |
2ND YR |
1ST 6 YRS |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
TOTAL |
|
|
|
DEPARTMENT FISCAL IMPACT NOTES: Click or tap here to enter text.
CONTRACT INFORMATION:
|
ORIGINAL |
|
CONTRACT # |
PW 24-027SB |
AMOUNT |
$4,040,000.00 |
|
AMENDMENT |
1 |
CONTRACT # |
PW 24-027SB |
AMOUNT |
$12,354.58 |
|
AMENDMENT |
2 |
CONTRACT # |
PW 24-027SB |
AMOUNT |
$71,578.14 |
|
AMENDMENT |
3 |
CONTRACT # |
PW 24-027SB |
AMOUNT |
$7,040.92 |
|
AMENDMENT |
4 |
CONTRACT # |
PW 24-027SB |
AMOUNT |
$16,843.95 |
|
AMENDMENT |
5 |
CONTRACT # |
PW 24-027SB |
AMOUNT |
$200,329.05 |
|
AMENDMENT |
6 |
CONTRACT # |
PW 24-027SB |
AMOUNT |
$143,596.21 |
|
AMENDMENT |
7 |
CONTRACT # |
PW 24-027SB |
AMOUNT |
$106,047.50 |
|
AMENDMENT |
8 |
CONTRACT # |
PW 24-027SB |
AMOUNT |
$53,786.28 |
|
AMENDMENT |
9 |
CONTRACT # |
PW 24-027SB |
AMOUNT |
$123,892.39 |
|
AMENDMENT |
10 |
CONTRACT # |
PW 24-027SB |
AMOUNT |
$116,751.01 |
|
AMENDMENT |
11 |
CONTRACT # |
PW 24-027SB |
AMOUNT |
$126,919.65 |
|
AMENDMENT |
12 |
CONTRACT # |
PW 24-027SB |
AMOUNT |
$63,703.30 |
|
AMENDMENT |
13 |
CONTRACT # |
PW 24-027SB |
AMOUNT |
$87,029.01 |
|
AMENDMENT |
14 |
CONTRACT # |
PW 24-027SB |
AMOUNT |
$90,718.61 |
|
AMENDMENT |
15 |
CONTRACT # |
PW 24-027SB |
AMOUNT |
$86,707.91 |
|
AMENDMENT |
16 |
CONTRACT # |
PW 24-027SB |
AMOUNT |
$130,019.49 |
|
AMENDMENT |
17 |
CONTRACT # |
PW 24-027SB |
AMOUNT |
$55,849.00 |
|
AMENDMENT |
18 |
CONTRACT # |
PW 24-027SB |
AMOUNT |
$114,305.40 |
|
AMENDMENT |
19 |
CONTRACT # |
PW 24-027SB |
AMOUNT |
$63,031.00 |
|
AMENDMENT |
20 |
CONTRACT # |
PW 24-027SB |
AMOUNT |
$123,529.00 |
|
AMENDMENT |
21 |
CONTRACT # |
PW 24-027SB |
AMOUNT |
$72,777.00 |
|
AMENDMENT |
22 |
CONTRACT # |
PW 24-027SB |
AMOUNT |
$11,595.00 |
|
AMENDMENT |
23 |
CONTRACT # |
PW 24-027SB |
AMOUNT |
$683,833.00 |
|
AMENDMENT |
24 |
CONTRACT # |
PW 24-027SB |
AMOUNT |
$55,593.00 |
|
AMENDMENT |
25 |
CONTRACT # |
PW 24-027SB |
AMOUNT |
$37,182.00 |
|
|
|
|
|
TOTAL |
$6,695,012.40 |
Contract Period
|
ORIGINAL |
START |
12/18/2024 |
END |
Final Project Acceptance Date |
|
AMENDMENT |
START |
Upon Execution |
END |
Same - Unchanged |
OTHER DEPARTMENTAL REVIEW/COMMENTS: Click or tap here to enter text.
|