File #: 2026-0176    Version: 1
Type: Motion Status: Consent Agenda
File created: 1/9/2026 In control: General Legislative Session
On agenda: 1/28/2026 Final action:
Title: Motion 26-039, approving and authorizing the County Executive to execute the Right-Of-Way Plan for Larson Road Bridge 101 Seismic Retrofit Project; RC1805; UPI# 23-0008
Attachments: 1. Proposed Motion 26-039, 2. Staff Report, 3. Funding Estimate, 4. Motion Assignment Slip

 

 

Executive/Council Action Form (ECAF)

 

 

ITEM TITLE:

Title

Motion 26-039, approving and authorizing the County Executive to execute the Right-Of-Way Plan for Larson Road Bridge 101 Seismic Retrofit Project; RC1805; UPI# 23-0008

body

DEPARTMENT:  Public Works

 

ORIGINATOR:  Makhan Ranu, P.E.

 

EXECUTIVE RECOMMENDATION:  Approved by Ken Klein 1/9/26

 

PURPOSE: Approval of this Right-of-Way (ROW) plan will allow the acquisition of Temporary Construction Easements (TCEs) for the Larson Road Bridge 101 Seismic Retrofit Project.

 

BACKGROUND: • The Larson Road Bridge 101 Seismic Retrofit Project is listed as item F.60 in the 2026 Annual Construction Plan.

• The County proposes to improve Larson Road Bridge 101 with a seismic retrofit for the bridge performance during seismic events.

• Construction of the project will require temporary easement on 5 parcels. The Right of Way phase is scheduled to begin in mid-2026.

• Estimates for ROW acquisition are based upon the Right of Way funding estimate provided by Engineering Services.

• The Right of Way phase of the project is funded with Federal Highway Administration (FHWA) funds with 13.5% local match after September 2026.

• The project is in Council District #1.

• LDA noticing was mailed on Dec 20, 2025

 

FISCAL IMPLICATIONS:

EXPEND: FUND, AGY, ORG, ACTY, OBJ, AU

CURRENT YR

2ND YR

1ST 6 YRS

102 50630324109 Appraisal

$10,000

 

$10,000

102 50630326101 Land Acquisition

 

$96,000

$96,000

 

 

 

 

 

 

 

 

TOTAL

$10,000

$96,000

$106,000

 

 

REVENUE: FUND, AGY, ORG, REV, SOURCE

CURRENT YR

2ND YR

1ST 6 YRS

102 3064442023 Federal Bridge Funding

$10,000

$83,040

$93,040

County Road Fund 102

 

$12,960

$12,960

 

 

 

 

 

 

 

 

TOTAL

$10,000

$96,000

$106,000

 

DEPARTMENT FISCAL IMPACT NOTES:  This project is included in the 2026-2031 Transportation Improvement Program (TIP) and also in the adopted 2026 Annual Construction Plan (ACP) as item F.60.

 

CONTRACT INFORMATION:

ORIGINAL

 

CONTRACT#

 

AMOUNT

 

AMENDMENT

 

CONTRACT#

 

AMOUNT

 

 

Contract Period

ORIGINAL

START

 

END

 

AMENDMENT

START

 

END

 

 

OTHER DEPARTMENTAL REVIEW/COMMENTS:  Reviewed/approved by Finance (Nathan Kennedy 1/9/26)