Title:
|
Authorizing the Executive to sign Change Order CO-33 to Bid PW-24-027SB for the Construction at the New Start Center of Everett with Marpac Construction LLC.
|
|
Attachments:
|
1. PW-24-027SB Certificate of Insurance, 2. PW-24-027SB Agreement, 3. PW24-027SB Tracking Log, 4. Motion 24-417, Amended, 5. PW-24-027SB Change Order 01, 6. PW-24-027SB Change Order 02, 7. PW-24-027SB Change Order 03, 8. PW-24-027SB Change Order 04, 9. PW-24-027SB Change Order 05, 10. PW-24-027SB Change Order 06, 11. PW-24-027SB Change Order 07, 12. PW-24-027SB Change Order 08, 13. PW-24-027SB Change Order 09, 14. PW-24-027SB Change Order 10, 15. PW-24-027SB Change Order 11, 16. PW-24-027SB Change Order 12, 17. PW-24-027SB Change Order 13, 18. PW-24-027SB Change Order 14, 19. PW-24-027SB Change Order 15, 20. PW-24-027SB Change Order 16, 21. PW-24-027SB Change Order 17, 22. PW-24-027SB Change Order 18, 23. PW-24-027SB Change Order 19, 24. PW-24-027SB Change Order 20, 25. PW-24-027SB Change Order 21, 26. PW-24-027SB Change Order 22, 27. PW-24-027SB Change Order 23, 28. PW-24-027SB Change Order 24, 29. PW-24-027SB Change Order 25, 30. PW-24-027SB Change Order 26, 31. PW-24-027SB Change Order 27, 32. PW-24-027SB Change Order 28, 33. PW-24-027SB Change Order 29, 34. PW-24-027SB Change Order 30, 35. PW-24-027SB Change Order 31, 36. PW-24-027SB Change Order 32, 37. PW-24-027SB Change Order 33 - SIGNED
|
Executive/Council Action Form (ECAF)
ITEM TITLE:
Title
Authorizing the Executive to sign Change Order CO-33 to Bid PW-24-027SB for the Construction at the New Start Center of Everett with Marpac Construction LLC.
body
DEPARTMENT: Facilities and Fleet Management
ORIGINATOR: Lance Meinhold
EXECUTIVE RECOMMENDATION: Approved
PURPOSE: To obtain Executive approval of Change Order 33 to Marpac Construction.
BACKGROUND: The County and Marpac Construction entered into an agreement on December 18th, 2024, for the construction phase of the New Start Center of Everett. The bid documents missed the specification for the replacement handwash sink. At the bid walk the contractor assumed the existing sink could be reused. It became apparent the sink could not be removed and reused during the course of construction. Rockwool was removed from the demising walls between the residential room during the moisture remediation process and after the bid was issued. The rockwool is required to provide the maintain the minimum level of fire-resistance rating protection between the residential units. The cost of this change has been negotiated down $4,984.
FISCAL IMPLICATIONS:
|
EXPEND: FUND, AGY, ORG, ACTY, OBJ, AU |
CURRENT YR |
2ND YR |
1ST 6 YRS |
|
002 5123116201 |
$68,858.00 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
TOTAL |
$68,858.00 |
|
|
|
REVENUE: FUND, AGY, ORG, REV, SOURCE |
CURRENT YR |
2ND YR |
1ST 6 YRS |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
TOTAL |
|
|
|
DEPARTMENT FISCAL IMPACT NOTES: Click or tap here to enter text.
CONTRACT INFORMATION:
|
ORIGINAL |
|
CONTRACT # |
PW 24-027SB |
AMOUNT |
$4,040,000.00 |
|
AMENDMENT |
1 |
CONTRACT # |
PW 24-027SB |
AMOUNT |
$12,354.58 |
|
AMENDMENT |
2 |
CONTRACT # |
PW 24-027SB |
AMOUNT |
$71,578.14 |
|
AMENDMENT |
3 |
CONTRACT # |
PW 24-027SB |
AMOUNT |
$7,040.92 |
|
AMENDMENT |
4 |
CONTRACT # |
PW 24-027SB |
AMOUNT |
$16,843.95 |
|
AMENDMENT |
5 |
CONTRACT # |
PW 24-027SB |
AMOUNT |
$200,329.05 |
|
AMENDMENT |
6 |
CONTRACT # |
PW 24-027SB |
AMOUNT |
$143,596.21 |
|
AMENDMENT |
7 |
CONTRACT # |
PW 24-027SB |
AMOUNT |
$106,047.50 |
|
AMENDMENT |
8 |
CONTRACT # |
PW 24-027SB |
AMOUNT |
$53,786.28 |
|
AMENDMENT |
9 |
CONTRACT # |
PW 24-027SB |
AMOUNT |
$123,892.39 |
|
AMENDMENT |
10 |
CONTRACT # |
PW 24-027SB |
AMOUNT |
$116,751.01 |
|
AMENDMENT |
11 |
CONTRACT # |
PW 24-027SB |
AMOUNT |
$126,919.65 |
|
AMENDMENT |
12 |
CONTRACT # |
PW 24-027SB |
AMOUNT |
$63,703.30 |
|
AMENDMENT |
13 |
CONTRACT # |
PW 24-027SB |
AMOUNT |
$87,029.01 |
|
AMENDMENT |
14 |
CONTRACT # |
PW 24-027SB |
AMOUNT |
$90,718.61 |
|
AMENDMENT |
15 |
CONTRACT # |
PW 24-027SB |
AMOUNT |
$86,707.91 |
|
AMENDMENT |
16 |
CONTRACT # |
PW 24-027SB |
AMOUNT |
$130,019.49 |
|
AMENDMENT |
17 |
CONTRACT # |
PW 24-027SB |
AMOUNT |
$55,849.00 |
|
AMENDMENT |
18 |
CONTRACT # |
PW 24-027SB |
AMOUNT |
$114,305.40 |
|
AMENDMENT |
19 |
CONTRACT # |
PW 24-027SB |
AMOUNT |
$63,031.00 |
|
AMENDMENT |
20 |
CONTRACT # |
PW 24-027SB |
AMOUNT |
$123,529.00 |
|
AMENDMENT |
21 |
CONTRACT # |
PW 24-027SB |
AMOUNT |
$72,777.00 |
|
AMENDMENT |
22 |
CONTRACT # |
PW 24-027SB |
AMOUNT |
$11,595.00 |
|
AMENDMENT |
23 |
CONTRACT # |
PW 24-027SB |
AMOUNT |
$683,833.00 |
|
AMENDMENT |
24 |
CONTRACT # |
PW 24-027SB |
AMOUNT |
$55,593.00 |
|
AMENDMENT |
25 |
CONTRACT # |
PW 24-027SB |
AMOUNT |
$37,182.00 |
|
AMENDMENT |
26 |
CONTRACT # |
PW 24-027SB |
AMOUNT |
$12,244.00 |
|
AMENDMENT |
27 |
CONTRACT # |
PW 24-027SB |
AMOUNT |
$45,111.00 |
|
AMENDMENT |
28 |
CONTRACT # |
PW 24-027SB |
AMOUNT |
$46,191.00 |
|
AMENDMENT |
29 |
CONTRACT # |
PW 24-027SB |
AMOUNT |
$72.00 |
|
AMENDMENT |
30 |
CONTRACT # |
PW 24-027SB |
AMOUNT |
$25,316.00 |
|
AMENDMENT |
31 |
CONTRACT # |
PW 24-027SB |
AMOUNT |
$106,683.00 |
|
AMENDMENT |
32 |
CONTRACT # |
PW 24-027SB |
AMOUNT |
$89,575.00 |
|
AMENDMENT |
33 |
CONTRACT # |
PW 24-027SB |
AMOUNT |
$68,858.00 |
|
|
|
|
|
TOTAL |
$7,089,062.40 |
Contract Period
|
ORIGINAL |
START |
12/18/2024 |
END |
Final Project Acceptance Date |
|
AMENDMENT |
START |
Upon Execution |
END |
Same - Unchanged |
OTHER DEPARTMENTAL REVIEW/COMMENTS: Click or tap here to enter text.
|