Snohomish Logo
File #: 2024-2993    Version: 1
Type: Motion Status: Pending Executive Signature
File created: 11/18/2024 In control: General Legislative Session
On agenda: 12/4/2024 Final action: 12/4/2024
Title: Motion 24-491, authorizing approval of Services Agreement between Snohomish County and Ketchum Shores Improvement Club to cost share for lake management services
Attachments: 1. Motion 24-491, 2. Staff Report, 3. Agreement (PENDING EXECUTIVE SIGNATURE), 4. Motion Assignment Slip

 

 

Executive/Council Action Form (ECAF)

 

 

ITEM TITLE:

Title

Motion 24-491, authorizing approval of Services Agreement between Snohomish County and Ketchum Shores Improvement Club to cost share for lake management services

body

DEPARTMENT:  Conservation & Natural Resources/Surface Water Management

 

ORIGINATOR:  Connie Price/Marisa Burghdoff

 

EXECUTIVE RECOMMENDATION:  Lacey Harper 11/21/24

 

PURPOSE: To authorize County Executive to execute Services Agreement between the County and Ketchum Shores Improvement Club to cost share for lake management services.

 

BACKGROUND: The County and the Ketchum Shores Improvement Club are collaborating to conduct lake restoration activities in Lake Ketchum to manage and control blue-green and toxic algae blooms and phosphorus pollution. The non-profit Club consists of members who are lake area residents with the mission of working together for the health and protection of Lake Ketchum. The County will perform restoration activities as set forth in Section II of the Agreement.  This Agreement establishes the relative contribution of the County and the Club from each funding source and the terms and conditions by which the Club is to compensate the County as follows:  The County shall pay sixty percent (60%) and the Club shall pay forty percent (40%) of the annual costs of Project Services, up to a combined maximum of One Hundred Thousand Dollars ($100,000.00) per year. In no event shall the County pay more than $60,000.00 annually for Project Services. The Club shall pay one hundred percent (100%) of any annual costs of Project Services that exceed $100,000.00. In the event Grant Funds are available, the Grant Funds shall be applied first as payment for the annual costs of Project Services. Thereafter, the County shall pay 60% and the Club shall pay 40% for any remaining costs up to a combined maximum of $100,000.00. For the Club’s share of the annual costs, the Lake Ketchum Service Charges established under SCC25.20.055 will be applied to the Club’s total payment amount first with any remaining costs to be paid using funds collected separately by the Club.

 

FISCAL IMPLICATIONS:

EXPEND: FUND, AGY, ORG, ACTY, OBJ, AU

CURRENT YR

2ND YR

1ST 6 YRS

415 50951144101 (County)

$88,300

$100,000

$588,300

 

 

 

 

 

 

 

 

 

 

 

 

TOTAL

$88,300

$100,000

$588,300

 

 

REVENUE: FUND, AGY, ORG, REV, SOURCE

CURRENT YR

2ND YR

1ST 6 YRS

415 3095111770

$52,980

$60,000

$352,980

415 3095111776

$20,240

$20,240

$121,440

415 3095113840 (WO450-R-3840)

$35,320

$19,760

 

 

 

 

 

TOTAL

$88,300

$100,000

$588,300

 

DEPARTMENT FISCAL IMPACT NOTES:  Funding for Project Services will come from a combination of the following funding sources: 1) surface water management utility service charges collected by the County under Snohomish County Code (SCC) 25.20.020; 2) service charges collected by the County specifically for Lake Ketchum restoration under SCC 25.20.055; 3) funds collected separately by the Club; and 4) grant funding where available and applicable to this Project.

 

CONTRACT INFORMATION:

ORIGINAL

X

CONTRACT#

N/A

AMOUNT

$233,000

AMENDMENT

 

CONTRACT#

 

AMOUNT

 

 

Contract Period

ORIGINAL

START

Date of Execution

END

12/31/2029

AMENDMENT

START

 

END

 

 

OTHER DEPARTMENTAL REVIEW/COMMENTS:  Reviewed/approved by:  Finance (Nathan Kennedy 11/20/24) and Prosecuting Attorney’s Office as to Form Only (Jessica Kraft-Klehm 11/5/24).