Legislation Details

File #: 2025-3381    Version: 1
Type: Motion Status: Approved
File created: 10/17/2025 In control: General Legislative Session
On agenda: 11/12/2025 Final action: 11/12/2025
Title: Motion 25-502, authorizing the County Executive to sign a Professional Services Agreement with Geoengineers Inc. for Paine Field former Fire Pit Agreed Order Implementation at Snohomish County Airport at Paine Field
Attachments: 1. Motion 25-502, 2. Staff Report, 3. Agreement - SIGNED, 4. Certificate of Insurance Liability, 5. Motion Assignment Slip

Executive/Council Action Form (ECAF 2025-3381)

 

 

ITEM TITLE:

Title

Motion 25-502, authorizing the County Executive to sign a Professional Services Agreement with Geoengineers Inc. for Paine Field former Fire Pit Agreed Order Implementation at Snohomish County Airport at Paine Field

body

DEPARTMENT:  Airport

 

ORIGINATOR:  Andrew Rardin

 

EXECUTIVE RECOMMENDATION:  Approved by Mike Fong 10/22/25

 

PURPOSE: This is a multi-year contract with GeoEngineers Inc. to assist in the implementation of the Department of Ecology Agreed Order (AO) for the Fire Pit PFAS Site.

 

BACKGROUND:

•                     This Agreement is the product of County RFQ-25-0504BC. GeoEngineers Inc. was selected as the most qualified company to perform the services required by the Department of Ecology Agreed Order.

•                     Snohomish County Airport has been investigating environmental contamination at the Former Fire Pit Site since 1998.

•                     On May 27, 2025, Ecology provided written notice that the Airport is a Potentially Liable Party (PLP) for the environmental contamination at the former Fire Pit Training Pit.

•                     The Airport, with assistance of its attorneys, has negotiated an Agreed Order with the Department of Ecology that requires the County to undertake all actions for remedial work.

•                     This Agreement in the amount NTE $2,254,510 will perform the required services in the Agreed Order.

 

FISCAL IMPLICATIONS:

EXPEND: FUND, AGY, ORG, ACTY, OBJ, AU

CURRENT YR

2ND YR

1ST 3 YRS

ACAPI49-60-6301

$50,000.00

$1,000,000.00

$1,204,510.00

 

 

 

 

TOTAL

$50,000.00

$1,000,000.00

$1,204,510.00

 

 

REVENUE: FUND, AGY, ORG, REV, SOURCE

CURRENT YR

2ND YR

1ST 3 YRS

410-5216806301

$50,000.00

$1,000,000.00

$1,204,510.00

 

 

 

 

TOTAL

$50,000.00

$1,000,000.00

$1,204,510.00

 

DEPARTMENT FISCAL IMPACT NOTES:  Click or tap here to enter text.

 

CONTRACT INFORMATION:

ORIGINAL

X

CONTRACT#

GeoEngineer AO Impl.

AMOUNT

$2,254,510

AMENDMENT

 

CONTRACT#

 

AMOUNT

 

 

Contract Period

ORIGINAL         X

START

Upon Execition

END

12/31/2029

AMENDMENT

START

 

END

 

 

OTHER DEPARTMENTAL REVIEWCOMMENTS:   Reviewed/approved by Risk Management (Diane Baer 10/21/25), Finance (Nathan Kennedy 10/22/25), and Prosecuting Attorney’s Office as to form only (Michelle Corsi 10/7/25)