Legislation Details

File #: 2026-0548    Version: 1
Type: Executive Status: Executive Approved
File created: 2/19/2026 In control: Executive
On agenda: Final action: 3/6/2026
Title: Authorizing the County Executive to sign Change Order CO-28 to Bid PW-24-028SB with Lincoln Construction, Inc. for the Construction at the New Start Center of Edmonds.
Attachments: 1. PW-24-028SB Certificate of Insurance Renewed, 2. PW-24-028SB Agreement, 3. PW24-028SB Tracking Log, 4. Motion 24-417, Amended, 5. PW-24-028SB Change Order 01, 6. PW-24-028SB Change Order 02, 7. PW-24-028SB Change Order 03, 8. PW-24-028SB Change Order 04, 9. PW-24-028SB Change Order 05, 10. PW-24-028SB Change Order 06, 11. PW-24-028SB Change Order 07, 12. PW-24-028SB Change Order 08, 13. PW-24-028SB Change Order 09, 14. PW-24-028SB Change Order 10, 15. PW-24-028SB Change Order 11, 16. PW-24-028SB Change Order 12, 17. PW-24-028SB Change Order 13, 18. PW-24-028SB Change Order 14, 19. PW-24-028SB Change Order 15, 20. PW-24-028SB Change Order 16, 21. PW-24-028SB Change Order 17, 22. PW-24-028SB Change Order 18, 23. PW-24-028SB Change Order 19, 24. PW-24-028SB Change Order 20, 25. PW-24-028SB Change Order 21, 26. PW-24-028SB Change Order 22, 27. PW-24-028SB Change Order 23, 28. PW-24-028SB Change Order 24, 29. PW-24-028SB Change Order 25, 30. PW-24-028SB Change Order 26, 31. PW-24-028SB Change Order 27, 32. PW-24-028SB Change Order 28 - SIGNED
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

 

 

Executive/Council Action Form (ECAF)

 

 

ITEM TITLE:

Title

Authorizing the County Executive to sign Change Order CO-28 to Bid PW-24-028SB with Lincoln Construction, Inc. for the Construction at the New Start Center of Edmonds.

body

DEPARTMENT:  Facilities and Fleet

 

ORIGINATOR:  Lance Meinhold

 

EXECUTIVE RECOMMENDATION:  Approved

 

PURPOSE: To obtain Executive approval of Change Order 28 to Lincoln Construction, Inc.

 

BACKGROUND: The County and Lincoln Construction Inc. (LCi) entered into an agreement on December 19th, 2024, for the construction phase of the New Start Center of Edmonds. Plumbing angle stops were discovered to be broken during the course of construction. Water to the building had been turned off until construction repairs were underway. The broken angle stops could not have been found prior to water being turned back on. The existing wiring from existing panel to existing panel was not able to reach from new panel to new panel due to panel sizes. The condition could not be verified until the walls were opened up during construction. Multiple electrical junction boxes and receptacle boxes in the walls were discovered have been damaged in their existing conditions. The boxes were not visible until plates were removed for new connections during the course of construction. The electricians are required to replace the damaged boxes for fire-life safety reasons. Multiple electrical receptacles and switches were discovered to have been cracked or broken. The broken devices were located randomly throughout the building and were not readily apparent during the bid walk. The automated door operators were not shown on the electrical drawings issued with the bid set. The existing resident room doors had oversized holes due to multiple lockset having been installed in them at various times in the past. A trim kit was needed to cover the holes. The trim kits are far less expensive than replacing the doors. The project also needed an encoder to program the door locks. The cost for this change order has been negotiated down from $93,108.00.

 

FISCAL IMPLICATIONS:

EXPEND: FUND, AGY, ORG, ACTY, OBJ, AU

CURRENT YR

2ND YR

1ST 6 YRS

002 5123116201

$77,873.00

 

 

 

 

 

 

 

 

 

 

 

 

 

 

TOTAL

$77,873.00

 

 

 

 

REVENUE: FUND, AGY, ORG, REV, SOURCE

CURRENT YR

2ND YR

1ST 6 YRS

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

TOTAL

 

 

 

 

DEPARTMENT FISCAL IMPACT NOTES:  Click or tap here to enter text.

 

CONTRACT INFORMATION:

ORIGINAL

 

CONTRACT#

PW24-028SB

AMOUNT

$2,474,000.00

AMENDMENT

1

CONTRACT#

PW24-028SB

AMOUNT

$547,000.00

AMENDMENT

2

CONTRACT#

PW24-028SB

AMOUNT

$128,884.00

AMENDMENT

3

CONTRACT#

PW24-028SB

AMOUNT

$-46,570.00

AMENDMENT

4

CONTRACT#

PW24-028SB

AMOUNT

$13,099.00

AMENDMENT

5

CONTRACT#

PW24-028SB

AMOUNT

$163,150.00

AMENDMENT

6

CONTRACT#

PW24-028SB

AMOUNT

$32,132.00

AMENDMENT

7

CONTRACT#

PW24-028SB

AMOUNT

$160,006.00

AMENDMENT

8

CONTRACT#

PW24-028SB

AMOUNT

$70,783.00

AMENDMENT

9

CONTRACT#

PW24-028SB

AMOUNT

$24,452.00

AMENDMENT

10

CONTRACT#

PW24-028SB

AMOUNT

$16,836.00

AMENDMENT

11

CONTRACT#

PW24-028SB

AMOUNT

$5,416.00

AMENDMENT

12

CONTRACT#

PW24-028SB

AMOUNT

$39,090.00

AMENDMENT

13

CONTRACT#

PW24-028SB

AMOUNT

$43,262.00

AMENDMENT

14

CONTRACT#

PW24-028SB

AMOUNT

$101,282.00

AMENDMENT

15

CONTRACT#

PW24-028SB

AMOUNT

$103,622.00

AMENDMENT

16

CONTRACT#

PW24-028SB

AMOUNT

$59,540.00

AMENDMENT

17

CONTRACT#

PW24-028SB

AMOUNT

$4,100.00

AMENDMENT

18

CONTRACT#

PW24-028SB

AMOUNT

$20,602.00

AMENDMENT

19

CONTRACT#

PW24-028SB

AMOUNT

$25,517.00

AMENDMENT

20

CONTRACT#

PW24-028SB

AMOUNT

$79,882.00

AMENDMENT

21

CONTRACT#

PW24-028SB

AMOUNT

$16,452.00

AMENDMENT

22

CONTRACT#

PW24-028SB

AMOUNT

$82,046.00

AMENDMENT

23

CONTRACT#

PW24-028SB

AMOUNT

$95,876.00

AMENDMENT

24

CONTRACT#

PW24-028SB

AMOUNT

$72,022.00

AMENDMENT

25

CONTRACT#

PW24-028SB

AMOUNT

$134,345.00

AMENDMENT

26

CONTRACT#

PW24-028SB

AMOUNT

$28,327.00

AMENDMENT

27

CONTRACT#

PW24-028SB

AMOUNT

$13,933.00

AMENDMENT

28

CONTRACT#

PW24-028SB

AMOUNT

$77,873.00

TOTAL

 

 

 

 

$4,586,959.00

 

Contract Period

ORIGINAL

START

12/19/2024

END

Final Project Acceptance Date

AMENDMENT

START

Upon Execution

END

Same - Unchanged

 

OTHER DEPARTMENTAL REVIEW/COMMENTS:  Click or tap here to enter text.