Title:
|
Authorizing the County Executive to sign Change Order CO-23 to Bid PW-24-028SB with Lincoln Construction, Inc. for the Construction at the New Start Center of Edmonds.
|
|
Attachments:
|
1. PW-24-028SB Certificate of Insurance Renewed, 2. PW-24-028SB Agreement, 3. PW24-028SB Tracking Log, 4. Motion 24-417, Amended, 5. PW-24-028SB Change Order 01, 6. PW-24-028SB Change Order 02, 7. PW-24-028SB Change Order 03, 8. PW-24-028SB Change Order 04, 9. PW-24-028SB Change Order 05, 10. PW-24-028SB Change Order 06, 11. PW-24-028SB Change Order 07, 12. PW-24-028SB Change Order 08, 13. PW-24-028SB Change Order 09, 14. PW-24-028SB Change Order 10, 15. PW-24-028SB Change Order 11, 16. PW-24-028SB Change Order 12, 17. PW-24-028SB Change Order 13, 18. PW-24-028SB Change Order 14, 19. PW-24-028SB Change Order 15, 20. PW-24-028SB Change Order 16, 21. PW-24-028SB Change Order 17, 22. PW-24-028SB Change Order 18, 23. PW-24-028SB Change Order 19, 24. PW-24-028SB Change Order 20, 25. PW-24-028SB Change Order 21, 26. PW-24-028SB Change Order 22 - ECAF 2025-3881, 27. PW-24-028SB Change Order 23 - Proposed, 28. PW-24-028SB Change Order 23 - Exec Signed
|
Executive/Council Action Form (ECAF)
ITEM TITLE:
Title
Authorizing the County Executive to sign Change Order CO-23 to Bid PW-24-028SB with Lincoln Construction, Inc. for the Construction at the New Start Center of Edmonds.
body
DEPARTMENT: Facilities and Fleet
ORIGINATOR: Lance Meinhold
EXECUTIVE RECOMMENDATION: Approved
PURPOSE: To obtain Executive approval of Change Order 23 to Lincoln Construction, Inc.
BACKGROUND: The County and Lincoln Construction Inc. (LCi) entered into an agreement on December 19th, 2024, for the construction phase of the New Start Center of Edmonds. The fire sprinkler system was completely destroyed during a hard-freeze event during the meth decontamination process. This change order is for the gypsum board replacement required to allow access to and recover the sprinkler pipes. The change order will be submitted for insurance reimbursement. The costs have been negotiated down $8,684.27.
FISCAL IMPLICATIONS:
|
EXPEND: FUND, AGY, ORG, ACTY, OBJ, AU |
CURRENT YR |
2ND YR |
1ST 6 YRS |
|
124 509044666201 |
$95,876.00 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
TOTAL |
$95,876.00 |
|
|
|
REVENUE: FUND, AGY, ORG, REV, SOURCE |
CURRENT YR |
2ND YR |
1ST 6 YRS |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
TOTAL |
|
|
|
DEPARTMENT FISCAL IMPACT NOTES: Click or tap here to enter text.
CONTRACT INFORMATION:
|
ORIGINAL |
|
CONTRACT# |
PW24-028SB |
AMOUNT |
$2,474,000.00 |
|
AMENDMENT |
1 |
CONTRACT# |
PW24-028SB |
AMOUNT |
$547,000.00 |
|
AMENDMENT |
2 |
CONTRACT# |
PW24-028SB |
AMOUNT |
$128,884.00 |
|
AMENDMENT |
3 |
CONTRACT# |
PW24-028SB |
AMOUNT |
$-46,570.00 |
|
AMENDMENT |
4 |
CONTRACT# |
PW24-028SB |
AMOUNT |
$13,099.00 |
|
AMENDMENT |
5 |
CONTRACT# |
PW24-028SB |
AMOUNT |
$163,150.00 |
|
AMENDMENT |
6 |
CONTRACT# |
PW24-028SB |
AMOUNT |
$32,132.00 |
|
AMENDMENT |
7 |
CONTRACT# |
PW24-028SB |
AMOUNT |
$160,006.00 |
|
AMENDMENT |
8 |
CONTRACT# |
PW24-028SB |
AMOUNT |
$70,783.00 |
|
AMENDMENT |
9 |
CONTRACT# |
PW24-028SB |
AMOUNT |
$24,452.00 |
|
AMENDMENT |
10 |
CONTRACT# |
PW24-028SB |
AMOUNT |
$16,836.00 |
|
AMENDMENT |
11 |
CONTRACT# |
PW24-028SB |
AMOUNT |
$5,416.00 |
|
AMENDMENT |
12 |
CONTRACT# |
PW24-028SB |
AMOUNT |
$39,090.00 |
|
AMENDMENT |
13 |
CONTRACT# |
PW24-028SB |
AMOUNT |
$43,262.00 |
|
AMENDMENT |
14 |
CONTRACT# |
PW24-028SB |
AMOUNT |
$101,282.00 |
|
AMENDMENT |
15 |
CONTRACT# |
PW24-028SB |
AMOUNT |
$103,622.00 |
|
AMENDMENT |
16 |
CONTRACT# |
PW24-028SB |
AMOUNT |
$59,540.00 |
|
AMENDMENT |
17 |
CONTRACT# |
PW24-028SB |
AMOUNT |
$4,100.00 |
|
AMENDMENT |
18 |
CONTRACT# |
PW24-028SB |
AMOUNT |
$20,602.00 |
|
AMENDMENT |
19 |
CONTRACT# |
PW24-028SB |
AMOUNT |
$25,517.00 |
|
AMENDMENT |
20 |
CONTRACT# |
PW24-028SB |
AMOUNT |
$79,882.00 |
|
AMENDMENT |
21 |
CONTRACT# |
PW24-028SB |
AMOUNT |
$16,452.00 |
|
AMENDMENT |
22 |
CONTRACT# |
PW24-028SB |
AMOUNT |
$82,046.00 |
|
AMENDMENT |
23 |
CONTRACT# |
PW24-028SB |
AMOUNT |
$95,876.00 |
|
TOTAL |
|
|
|
|
$4,260,459.00 |
Contract Period
|
ORIGINAL |
START |
12/19/2024 |
END |
Final Project Acceptance Date |
|
AMENDMENT |
START |
Upon Execution |
END |
Same - Unchanged |