Title: Motion 26-147, authorizing approval of Construction Change Order No. 2 for Kayak Point Phase 2 playground surfacing
Attachments: 1. Proposed Motion 26-147, 2. Change Order 2, 3. Change Order 1, 4. Agreement, 5. Certificate of Insurance, 6. Motion Assignment Slip
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

 

 

Executive/Council Action Form (ECAF)

 

 

ITEM TITLE:

Title

Motion 26-147, authorizing approval of Construction Change Order No. 2 for Kayak Point Phase 2 playground surfacing

body

DEPARTMENT:  DCNR/Parks and Recreation

 

ORIGINATOR:  Rob Marchand

 

EXECUTIVE RECOMMENDATION:  Approved by Tom Teigen 3/19/26

 

PURPOSE: Approval of Change Order 2 with OMA Construction Inc. for the Kayak Day Use Phase 2 project.  

 

BACKGROUND: Snohomish County Parks Department went out to bid for Kayak Day Use Phase 2 Bid No. PW-25-0495SB  with the playground as a bid alternative to ensure Parks had the funding to support the construction of the new playground. Parks received very competitive bids to install the playground and have funding to support the change from Engineered Wood Fiber to Synthetic turn to provide a more uniform and ADA compliant surfacing. The bid was awarded to OMA Construction Inc. in the amount of $3,605,000.00 (plus applicable sales tax) on December 4, 2025.  Change Order 2 is proposed for 369,972.25 (plus applicable sales tax) and is for  labor and materials to  Replace Engineered Wood Fiber playground surfacing and add 11,614 square feet of Forever Lawn Playground Grass Ultra with 3" safety pad and certified for a 10-foot critical fall height. Includes Envirofill infill, edging in composite board, and seaming tape.

 

FISCAL IMPLICATIONS:

EXPEND: FUND, AGY, ORG, ACTY, OBJ, AU

CURRENT YR

2ND YR

1ST 6 YRS

309-51094610326599

369,972.25

 

369,972.25

 

 

 

 

 

 

 

 

 

 

 

 

TOTAL

369,972.25

 

369,972.25

 

 

REVENUE: FUND, AGY, ORG, REV, SOURCE

CURRENT YR

2ND YR

1ST 6 YRS

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

TOTAL

 

 

 

 

DEPARTMENT FISCAL IMPACT NOTES:  Click or tap here to enter text.

 

CONTRACT INFORMATION:

ORIGINAL

X

CONTRACT#

 

AMOUNT

$3,605,000.00

AMENDMENT

X

CONTRACT#

CO #1

AMOUNT

$315,416.44

AMENDMENT

x

CONTRACT#

CO#2

AMOUNT

$369,972.25

 

Contract Period

ORIGINAL

START

December 4, 2025

END

October 14, 2026

AMENDMENT

START

 

END

 

 

OTHER DEPARTMENTAL REVIEW/COMMENTS:  Reviewed/approved by:  Risk Management (Stephanie Rousseau 3/18/26) and Finance (Nathan Kennedy 3/19/26)