Legislation Details

File #: 2026-0293    Version: 1
Type: Executive Status: Executive Approved
File created: 1/23/2026 In control: Executive
On agenda: Final action: 2/3/2026
Title: Authorizing the Executive to sign Change Order CO-31 to Bid PW-24-027SB for the Construction at the New Start Center of Everett with Marpac Construction LLC.
Attachments: 1. PW-24-027SB Certificate of Insurance, 2. PW-24-027SB Agreement, 3. PW24-027SB Tracking Log, 4. Motion 24-417, Amended, 5. PW-24-027SB Change Order 01, 6. PW-24-027SB Change Order 02, 7. PW-24-027SB Change Order 03, 8. PW-24-027SB Change Order 04, 9. PW-24-027SB Change Order 05, 10. PW-24-027SB Change Order 06, 11. PW-24-027SB Change Order 07, 12. PW-24-027SB Change Order 08, 13. PW-24-027SB Change Order 09, 14. PW-24-027SB Change Order 10, 15. PW-24-027SB Change Order 11, 16. PW-24-027SB Change Order 12, 17. PW-24-027SB Change Order 13, 18. PW-24-027SB Change Order 14, 19. PW-24-027SB Change Order 15, 20. PW-24-027SB Change Order 16, 21. PW-24-027SB Change Order 17, 22. PW-24-027SB Change Order 18, 23. PW-24-027SB Change Order 19, 24. PW-24-027SB Change Order 20, 25. PW-24-027SB Change Order 21, 26. PW-24-027SB Change Order 22, 27. PW-24-027SB Change Order 23, 28. PW-24-027SB Change Order 24, 29. PW-24-027SB Change Order 25, 30. PW-24-027SB Change Order 26, 31. PW-24-027SB Change Order 27, 32. PW-24-027SB Change Order 28, 33. PW-24-027SB Change Order 29, 34. PW-24-027SB Change Order 30, 35. PW-24-027SB Change Order 31 - SIGNED
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

 

 

Executive/Council Action Form (ECAF)

 

 

ITEM TITLE:

Title

Authorizing the Executive to sign Change Order CO-31 to Bid PW-24-027SB for the Construction at the New Start Center of Everett with Marpac Construction LLC.

body

DEPARTMENT:  Facilities and Fleet Management

 

ORIGINATOR:  Lance Meinhold

 

EXECUTIVE RECOMMENDATION:  Approved

 

PURPOSE: To obtain Executive approval of Change Order 31 to Marpac Construction.

 

BACKGROUND:  The County and Marpac Construction entered into an agreement on December 18th, 2024, for the construction phase of the New Start Center of Everett. The City of Everett Building Inspector noticed the cast iron bathtubs in the back building extend to the wood frame stud walls. The condition stops the gypsum board, which should extend to the floor deck to create a UL listed fire-resistance rated and tested assembly. The entire project team met with the Building Official onsite to discuss possible solutions. The meeting took three weeks to arrange as the Building Official was experiencing health issues and is the only person legally allowed to make the desired type of code determination. The result was the requirements to provide fire-rate caulking between the cast iron and the gypsum board. Cast iron is non-flammable and has a higher melting point than the PVC fire sprinkler piping. There is also an argument to be made that the tub to wall joints were existing conditions which are not subject to the requirement of the new building code, essentially being grandfathered into compliance. Also, the condition also existing in the front building, but was not required to be upgraded. The cost of the change has been negotiated down by $7,702. The work itself will take approximately one week. The subcontractors preforming the work were reassigned to another project while we awaited the meeting with the building official. All told, the project lost 37 days to the critical path.

 

FISCAL IMPLICATIONS:

EXPEND: FUND, AGY, ORG, ACTY, OBJ, AU

CURRENT YR

2ND YR

1ST 6 YRS

002 5123116201

$106,683.00

 

 

 

 

 

 

 

 

 

 

 

 

 

 

TOTAL

$106,683.00

 

 

 

 

REVENUE: FUND, AGY, ORG, REV, SOURCE

CURRENT YR

2ND YR

1ST 6 YRS

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

TOTAL

 

 

 

 

DEPARTMENT FISCAL IMPACT NOTES:  Click or tap here to enter text.

 

CONTRACT INFORMATION:

ORIGINAL

 

CONTRACT #

PW 24-027SB

AMOUNT

$4,040,000.00

AMENDMENT

1

CONTRACT #

PW 24-027SB

AMOUNT

$12,354.58

AMENDMENT

2

CONTRACT #

PW 24-027SB

AMOUNT

$71,578.14

AMENDMENT

3

CONTRACT #

PW 24-027SB

AMOUNT

$7,040.92

AMENDMENT

4

CONTRACT #

PW 24-027SB

AMOUNT

$16,843.95

AMENDMENT

5

CONTRACT #

PW 24-027SB

AMOUNT

$200,329.05

AMENDMENT

6

CONTRACT #

PW 24-027SB

AMOUNT

$143,596.21

AMENDMENT

7

CONTRACT #

PW 24-027SB

AMOUNT

$106,047.50

AMENDMENT

8

CONTRACT #

PW 24-027SB

AMOUNT

$53,786.28

AMENDMENT

9

CONTRACT #

PW 24-027SB

AMOUNT

$123,892.39

AMENDMENT

10

CONTRACT #

PW 24-027SB

AMOUNT

$116,751.01

AMENDMENT

11

CONTRACT #

PW 24-027SB

AMOUNT

$126,919.65

AMENDMENT

12

CONTRACT #

PW 24-027SB

AMOUNT

$63,703.30

AMENDMENT

13

CONTRACT #

PW 24-027SB

AMOUNT

$87,029.01

AMENDMENT

14

CONTRACT #

PW 24-027SB

AMOUNT

$90,718.61

AMENDMENT

15

CONTRACT #

PW 24-027SB

AMOUNT

$86,707.91

AMENDMENT

16

CONTRACT #

PW 24-027SB

AMOUNT

$130,019.49

AMENDMENT

17

CONTRACT #

PW 24-027SB

AMOUNT

$55,849.00

AMENDMENT

18

CONTRACT #

PW 24-027SB

AMOUNT

$114,305.40

AMENDMENT

19

CONTRACT #

PW 24-027SB

AMOUNT

$63,031.00

AMENDMENT

20

CONTRACT #

PW 24-027SB

AMOUNT

$123,529.00

AMENDMENT

21

CONTRACT #

PW 24-027SB

AMOUNT

$72,777.00

AMENDMENT

22

CONTRACT #

PW 24-027SB

AMOUNT

$11,595.00

AMENDMENT

23

CONTRACT #

PW 24-027SB

AMOUNT

$683,833.00

AMENDMENT

24

CONTRACT #

PW 24-027SB

AMOUNT

$55,593.00

AMENDMENT

25

CONTRACT #

PW 24-027SB

AMOUNT

$37,182.00

AMENDMENT

26

CONTRACT #

PW 24-027SB

AMOUNT

$12,244.00

AMENDMENT

27

CONTRACT #

PW 24-027SB

AMOUNT

$45,111.00

AMENDMENT

28

CONTRACT #

PW 24-027SB

AMOUNT

$46,191.00

AMENDMENT

29

CONTRACT #

PW 24-027SB

AMOUNT

$72.00

AMENDMENT

30

CONTRACT #

PW 24-027SB

AMOUNT

$25,316.00

AMENDMENT

31

CONTRACT #

PW 24-027SB

AMOUNT

$106,683.00

 

 

 

 

TOTAL

$6,930,629.40

 

Contract Period

ORIGINAL

START

12/18/2024

END

Final Project Acceptance Date

AMENDMENT

START

Upon Execution

END

Same - Unchanged

 

OTHER DEPARTMENTAL REVIEW/COMMENTS:  Click or tap here to enter text.